RAPID/Roadmap/9 (2)
Hydropower Environmental Review Overview (9)
The National Environmental Policy Act (NEPA) was signed into law on January 1, 1970. NEPA establishes national environmental policy and goals for the protection, maintenance, and enhancement of the environment and provides a process for implementing these goals within the federal agencies. A developer will be required to go through the NEPA process if the project involves a "major federal action A major federal action is defined as “an action that the agency carrying out such action determines is subject to substantial Federal control and responsibility.” 42 U.S.C. 4336e (10). The level and scope of the NEPA review will vary depending on the nature of the project and to what degree the federal government will be involved. Some actions and projects will receive a categorical exclusion while others may require a full Environmental Impact Statement (EIS).
NEPA review is handled by a "lead agency." A “lead agency" is the federal agency responsible for writing the main NEPA document(s) and coordinating with any other federal, state, or tribal agencies. The lead agency is expected to follow the guidelines prescribed by NEPA in 42 U.S.C. 4336a. An EA must not be longer than 75 pages, not including appendices or citations and it must be completed within one year. 42 U.S.C. 4336a. An EIS has a page limit of 150 pages, not including appendices or citations, or if it is of extraordinary complexity the limit is 300 pages, not including any appendices or citations. An EIS must be completed within two years of the start date identified in 42 U.S.C. 4336a. The deadline may be extended by the lead agency in consultation with the applicant for only so much additional time as is necessary to complete the environmental document. 42 U.S.C. 4336a (g). If the deadline is not met for either an EA or an EIS, a project sponsor may file a written petition with a court to compel the agency to act more quickly. 42 U.S.C. 4336a (g)(3).
For many hydropower projects, the lead agency will be the Federal Energy Regulatory Commission (FERC). However, under certain circumstances the lead agency will be the Bureau of Reclamation (BOR), the U.S. Army Corps of Engineers (USACE), or a federal land management agency such as the United States Forest Service (USFS) or the Bureau of Land Management (BLM). A hydropower project may be required to undergo more than one NEPA review, each with a different lead agency. This would occur if, for example, USACE does not sign on as a cooperating agency for FERC review and instead completes a separate NEPA review for Section 404 permitting. An approach such as this would produce two distinct NEPA documents each potentially incorporating the contents of the other by reference.
A “cooperating agency” means any federal, state, local, or tribal agency other than a lead agency which has jurisdiction by law or special expertise with respect to any environmental impact involved in a proposal (or a reasonable alternative) for legislation or other major federal action significantly affecting the quality of the human environment. For example, where FERC is the lead agency for purposes of completing the NEPA process for hydropower development on federal land, other federal agencies with jurisdiction or special expertise take on the role of a cooperating agency.
To comply with federal environmental regulation, the developer is also required to comply with state environmental laws. Many states have adopted their own environmental laws and regulations.
Potential environmental impacts from hydropower development that may occur during the site evaluation, construction, and operation phases of the project include:
- Vehicle emissions, volatile organic compound (VOC) releases from storage and transfer of vehicle/equipment fuels, carbon monoxide, nitrogen oxides and particulates from blasting activities, and fugitive dust from clearing, grading, excavating, and vehicle and equipment traffic;
- Noise disturbances from drilling, blasting, vehicle traffic, turbine, generator, and transformer can impact migration, feeding, and reproduction patterns in species;
- Direct and indirect impacts to cultural resources from surface disturbances or excavation, erosion, sedimentation, increased human access can increase exposure to contaminants, and interfere with behavioral activities of species;
- Direct and indirect impacts to ecological resources (vegetation, wildlife, aquatic biota and their habitats) from introduction of invasive species from vehicle traffic, fugitive dust, erosion and runoff from excavation can limit a plant’s ability to photosynthesize, and impact habitats. Construction of roads, canals, pipelines, and transmission rights-of-way can fragment wildlife habitats affecting feeding and reproduction behaviors. Construction of intakes and dams can significantly alter the river leading to habitat loss and degradation for aquatic species; and
- Water quality could also be affected by activities that cause soil erosion, including construction of the intake and dam, which could increase turbidity and suspended sediment transport.
Environmental Review Overview Process
9.1 – Does the Project Require a Major Federal Action?
For the National Environmental Policy Act (NEPA) to be triggered there must be a "major federal action" (action).
Major federal actions tend to fall within one of the following categories:
- Adoption of official policy, such as rules, regulations, and interpretations adopted pursuant to the Administrative Procedure Act, 5 U.S.C. § 551 et seq.; treaties and international conventions or agreements; formal documents establishing an agency's policies which will result in or substantially alter agency programs.
- Adoption of formal plans, such as official documents prepared or approved by federal agencies which guide or prescribe alternative uses of Federal resources, upon which future agency actions will be based.
- Adoption of programs, such as a group of concerted actions to implement a specific policy or plan; systematic and connected agency decisions allocating agency resources to implement a specific statutory program or executive directive.
- Approval of specific projects, such as construction or management activities located in a defined geographic area. Projects include actions approved by permit or other regulatory decision as well as federal and federally assisted activities.
Major federal actions include new and continuing activities, including projects and programs entirely or partly financed, assisted, conducted, regulated, or approved by federal agencies; new or revised agency rules, regulations, plans, policies, or procedures; and legislative proposals. 40 C.F.R. § 1508.1(q).
Major federal actions do not include:
- Agency activities or decisions with effects located entirely outside of the jurisdiction of the United States;
- Non discretionary activities or decisions made in accordance with the agency's statutory authority (i.e. ones that the agency has no choice but to make);
- Activities or decisions that do not result in final agency action under the Administrative Procedure Act or other statute that also includes a finality requirement;
- Judicial or administrative civil or criminal enforcement actions;
- Funding assistance solely in the form of general revenue sharing funds with no Federal agency control over the subsequent use of such funds;
- Non-Federal projects with minimal Federal funding or minimal Federal involvement where the agency does not exercise sufficient control and responsibility over the outcome of the project; and
- Loans, loan guarantees, or other forms of financial assistance where the Federal agency does not exercise sufficient control and responsibility over the effects of such assistance
40 C.F.R. § 1508.1(q). 42 U.S.C. 4336e (10).
In general, NEPA will be triggered if the project is on federal land, the federal government owns the mineral estate, the project receives federal funding or support, or if a federal permit is required. Within the context of hydropower development, NEPA will be triggered if the project requires an authorization from Federal Energy Regulatory Commission (FERC), the discharge of dredge or fill material into waters of the United States, a Lease of Power Privilege for generating hydropower on a Bureau of Reclamation (BOR) managed conduit or dam, or a right-of-way on federal lands outside an established FERC project boundary.
9.2 to 9.3 – Is Federal Energy Regulatory Commission the Lead Agency for the Major Federal Action?
Under NEPA, a “lead agency” is the agency preparing NEPA documentation or is the agency that has taken primary responsibility for coordinating the NEPA process. If FERC is the lead agency, then FERC will coordinate the NEPA process. This would typically be the case when any FERC authorization (permit or exemption) is required to develop or decommission a non-federal hydropower project. Under the Traditional Licensing Process, FERC’s typical NEPA process will be followed. Under the Alternative Licensing Process and the Integrated Licensing Process, the NEPA process is combined with the FERC licensing process. For more information, see:
9.4 to 9.5 – Is the U.S. Army Corps of Engineers the Lead Agency for the Major Federal Action?
If U.S. Army Corps of Engineers (USACE) is the lead agency, then it will coordinate the NEPA process. This would typically be the case for USACE issuance of a Section 404 permit for the discharge of dredge or fill material into waters of the U.S. For more information, see:
U.S. Army Corps of Engineers - NEPA Review:
9-FD-k
9.6 to 9.7 – Is the Bureau of Reclamation the Lead Agency for the Major Federal Action?
If the Bureau of Reclamation (BOR) is the lead agency, then it will coordinate the NEPA process. This would typically be the case if the BOR executes a Lease of Power Privilege for a non-FERC licensed project. 43 U.S.C. § 485h (c).
Bureau of Reclamation - NEPA Review:
9-FD-j
9.8 to 9.9 – Is the Department of Defense the Lead Agency for the Major Federal Action?
If the United States Department of Defense (DOD) is the lead agency, then it will coordinate the NEPA process. This would typically be the case if the DOD executes an Enhanced Use Lease for development of a renewable energy project on a military reservation or if the DOD grants a right-of-way for a transmission line outside of the FERC project boundary. For more information, see:
Department of Defense - NEPA Review:
9-FD-f
9.10 to 9.11 – Is the Bureau of Land Management the Lead Agency for the Major Federal Action?
If the Bureau of Land Management (BLM) is the lead agency, then it will coordinate the NEPA process. This would typically be the case if the BLM grants a right-of-way for a transmission line outside of the FERC project boundary. If the BLM decides to complete its own NEPA review, BLM may seek to incorporate any NEPA review completed by FERC when authorizing the project. For more information, see:
Bureau of Land Management - NEPA Review:
9-FD-a
9.12 to 9.13 – Is the U.S. Forest Service the Lead Agency for the Major Federal Action?
If the United States Forest Service (USFS) is the lead agency, then it will coordinate the NEPA process. This would typically be the case if the USFS grants a right-of-way for a transmission line outside of the FERC project boundary. If the USFS decides to complete its own NEPA review, USFS may seek to incorporate any NEPA review completed by FERC when authorizing the project. For more information, see:
United States Forest Service - NEPA Process:
9-FD-g
9.14 to 9.15 – Is the U.S. Fish and Wildlife Service the Lead Agency for the Major Federal Action?
If the United States Fish and Wildlife Service (FWS) is the lead agency, then it will coordinate the NEPA process. This would typically be the case if the FWS grants a right-of-way for a transmission line outside of the FERC project boundary. If the FWS decides to complete its own NEPA review, FWS may seek to incorporate any NEPA review completed by FERC when authorizing the project. For more information, see:
U.S. Fish and Wildlife Service - NEPA Review:
9-FD-l
9.16 to 9.17 – Is the National Park Service the Lead Agency for the Major Federal Action?
If the National Park Service (NPS) is the lead agency, then it will coordinate the NEPA process. This would typically be the case if the NPS grants a right-of-way for a transmission line outside of the FERC project boundary. If the NPS decides to complete its own NEPA review, NPS may seek to incorporate any NEPA review completed by FERC when authorizing the project. For more information, see:
National Park Service - NEPA Review:
9-FD-m
9.18 – Contact Other Federal Agencies for NEPA Review
If another federal agency is the lead agency for the major federal action then the developer will be required to contact that agency for its NEPA policies and procedures.
9.19 to 9.20 – Has an On-Site Evaluation Been Conducted?
The on-site evaluation process is intended to walk the developer through all of the required "environmental" considerations of a typical environmental review under NEPA. For more information, see:
On-Site Evaluation Overview: 10
9.21 – Initiate State Environmental Review
Most states have passed state environmental laws and regulations. Some states have an all-encompassing environmental review process while other states consider only certain issues.
Alaska
Alaska does not have a state specific environmental review process.
Arkansas
Arkansas does not have a state specific environmental review process.
California
In California, a hydropower project is subject to review pursuant to the California Environmental Quality Act. For more information, see:
Colorado
Colorado does not have a state specific environmental review process.
Illinois
Illinois does not have a state specific environmental review process.
Indiana
Indiana has a state specific environmental review process, but it only applies to state initiated projects and state funded projects. For more information on State Environmental Policy Act, but this act does not apply to state agencies in the Indiana Environmental Policy Act, see: I.C. § 13-2-4 and I.A.C. § 326-16.
Iowa
In Iowa, a hydropower developer may choose to comply with the state’s optional environmental process regulated by the Iowa Department of Natural Resources (IDNR). The developer may send a request for an environmental review to the IDNR, and IDNR will conduct an environmental review. The developer should include any pertinent details about the project in the request. More information on Iowa's developer-initiated environmental review process can be found on IDNR's Environmental Review for Natural Resources Website.
Kentucky
Kentucky does not have a state specific environmental process.
Louisiana
Louisiana does not have a state specific environmental review process.
Minnesota
In Minnesota, a hydropower project is subject to review pursuant to the Minnesota Environmental Policy Act. The scope of the environmental review depends on the size of the project and the lead agency in charge. For more information, see:
Mississippi
Mississippi does not have a state specific environmental review process
Missouri
Missouri does not have a state specific environmental review process. However, the Missouri Department of Conservation may review and provide comments on a proposed project under NEPA, as well as other federal laws and programs, such as the Fish and Wildlife Coordination Act, the Endangered Species Act, and the Clean Water Act. The Missouri Department of Natural Resources also participates in the NEPA process. Both agencies are able to assist developers in the selection of a project site.
New York
In New York, a hydropower project may be subject to review pursuant to the State Environmental Quality Review Act. For more information, see:
North Dakota
North Dakota does not have a state specific environmental review process.
Ohio
Ohio does not have a state specific environmental review process.
Pennsylvania
Pennsylvania does not have a state specific environmental review.
Tennessee
Tennessee does not have a state specific environmental review.
Vermont
Vermont does not have a state specific environmental review process.
Washington
In Washington, a hydropower project is subject to review pursuant to the Washington State Environmental Policy Act. For more information, see:
West Virginia
West Virginia does not have a state specific environmental review process.
Wisconsin
In Wisconsin, a hydropower project is subject to review pursuant to the Wisconsin Environmental Policy Act. 1 Wis. Stat. § 1.11. For more information, see:
Agencies
Contact Information
Suggest a contact using the Feedback button above.Suggest edits using the Feedback button above.
Regulations
- National Environmental Policy Act
- Title 40 CFR 1508 Terminology and Index
- Title 40 CFR 1506 Other Requirements of NEPA
- [[43 U.S.C. §485h New Projects
- Sale of Water and Electric Power]]
- Section 10 of the Rivers and Harbors Act of 1899 (33 U.S.C. 403)
- Executive Order 13807 – Establishing Discipline and Accountability in the Environmental Review and Permitting Process for Infrastructure (One Federal Decision)
- Memorandum of Understanding Implementing One Federal Decision Under Executive Order 13807
Edit
Federal Energy Regulatory Commission
Regional Office Hydropower Contacts
Visit Website
Edit
U.S. Army Corps of Engineers
Section 404 Regulatory Contacts
202-761-5903
Visit Website
Edit
U.S. Army Corps of Engineers
Section 408 Regulatory Contacts
202-761-5903
more information, or if,@usace.army.mil. Visit Website
Edit
Bureau of Reclamation
Hydropower Program: Power Resources Office Directory
Visit Website