RAPID/Geothermal/Oregon/Drilling & Well Development

From Open Energy Information

< RAPID‎ | Geothermal‎ | Oregon

RAPIDRegulatory and Permitting Information Desktop Toolkit
My Projects

Oregon Geothermal Drilling & Well Development(5-OR)

Developers seeking to commence drilling, redrilling, or deepening of a geothermal well must obtain a Geothermal Well Permit from the Oregon Department of Geology and Mineral Industries. The permitting process is regulated under O.R.S. 522. Developers seeking a Geothermal Well Permit must have completed the environmental review process for the proposed drilling and have secured a water right. The permitting process involves payment of fees, a bond, description of development area, and agency consultation. Permitted activities must commence with one year of the permit date.

Drilling, redrilling or deepening must begin within one year after the date of permit issuance or the permit shall expire. ORS 522.135(5). This term may be extended for a reasonable period (not to exceed one year). The permit is intended to allow for the commencement of drilling and drilling related activities (conductor pipe, well pad, access road construction, etc).

More Information

Determine Which State and Federal Permits Apply

Use this overview flowchart and following steps to learn which federal and state permits apply to your projects.


Permitting at a Glance

Oregon Federal

Drilling & Well Field Permit Agency: Oregon State Department of Geology and Mineral Industries Bureau of Land Management
Drilling & Well Field Permit: Developers seeking to commence drilling, redrilling, or deepening of a geothermal well must obtain a Geothermal Well Permit from the Oregon Department of Geology and Mineral Industries. [1] Geothermal Drilling Permit (Form 3260-002)