PRIMRE/Databases/Projects Database/Projects/Texel Wave Energy Pilot

From Open Energy Information
Abigales

Texel Wave Energy Pilot

The project began in 2018 as a three year plan to demonstrate the Slow Mill wave energy converter technology with an estimated cost of 4 million euros, 2.5 million of which were granted from the Wadden Fund. The deployment was part of a larger plan to power the Island of Texal with wave energy farms which at the time was estimated to require 10% Texals coastline, and eventually the whole of the Frisian islands in the same manner.

Plans were quickly set into motion with the deployment of a 50 tonne concrete anchor sunk roughly 4 kilometers off of Texals coastline in December of 2018 for later use with the 1:2.5 scale 40 kW pilot device dubbed "Slow Mill-40". The early launch of the anchor was used to determine the stability of its deployment as well as its impact on the local environment which was shown to increase life in the area. The actual Slow Mill-40 was commissioned for construction and 2020 and deployed for trials in 2022.

The demonstration was completed by 2024 with the removal of the Slow Mill-40 for dry bench testing and shortly after the concrete anchor. Both components are planned for deployment at an offshore site in Scheveningen once the dry tests are completed. Testing will be used to inform the developers of adjustments needed to the device for a 1:1 scale device currently planned to have a 400 kilowatt capacity for use in previously mentioned wave farm to power Texal.

SlowMill-40.jpg cdn.offshorewind.biz

Additional Information
Project Status
Is the project actively being planned or is deployed in the water (active)? Or was the project canceled or completed (inactive)?
Inactive
Project Life Cycle
Project Progress through life cycle:
  • Planned: Project has identified a deployment location and is preparing for deployment
  • Operational: Project is deployed in the water and is active
  • Completed: Project was previously deployed in the water
  • Decommissioned: Installation has been fully removed in accordance with regulations
  • Canceled: Project was canceled before being deployed in the water
Completed
Max Rated Power Capacity
The maximum amount of electricity that can be produced by project, based on available resources and device nameplate capacity.
.04 MW
Operational Duration
July 2022 - July 2024
Project Duration
2018 - 2024
Energy Resource
  • Wave
Project Scale
Sub-scale
Number of Devices
1
Grid Connectivity
Not Grid Connected
Waterbody
North Sea, Texal
Site Characteristics
Geographic characterization for the project location:
  • Open Ocean: Main body of ocean, not enclosed or partially enclosed by land
  • Coastal: Open water near the coast, spanning between land and shelf boundary
  • Enclosed Bay: water that is partially surrounded by land, with a mouth open to larger water
  • Constricted Channel: A channel where water flows quickly due to narrowing by the land
  • River: Water flowing from land towards a larger body of water
Coastal
Country
Netherlands
Last Modified
10 June 2025


This Project has the following MRE Devices

Filters:

Citation Formats

“Texel Wave Energy Pilot.” Marine Energy Projects Database: Projects, PRIMRE, United States Department of Energy, https://openei.org/wiki/PRIMRE/Databases/Projects_Database/Projects/Texel_Wave_Energy_Pilot. Accessed <day> <monthRoman> <year>.
Marine Energy Projects Database: Projects. <year>. "Texel Wave Energy Pilot." Accessed <monthRoman> <day>, <year>. https://openei.org/wiki/PRIMRE/Databases/Projects_Database/Projects/Texel_Wave_Energy_Pilot.