Texel Wave Energy Pilot
The project began in 2018 as a three year plan to demonstrate the Slow Mill wave energy converter technology with an estimated cost of 4 million euros, 2.5 million of which were granted from the Wadden Fund. The deployment was part of a larger plan to power the Island of Texal with wave energy farms which at the time was estimated to require 10% Texals coastline, and eventually the whole of the Frisian islands in the same manner.
Plans were quickly set into motion with the deployment of a 50 tonne concrete anchor sunk roughly 4 kilometers off of Texals coastline in December of 2018 for later use with the 1:2.5 scale 40 kW pilot device dubbed "Slow Mill-40". The early launch of the anchor was used to determine the stability of its deployment as well as its impact on the local environment which was shown to increase life in the area. The actual Slow Mill-40 was commissioned for construction and 2020 and deployed for trials in 2022.
The demonstration was completed by 2024 with the removal of the Slow Mill-40 for dry bench testing and shortly after the concrete anchor. Both components are planned for deployment at an offshore site in Scheveningen once the dry tests are completed. Testing will be used to inform the developers of adjustments needed to the device for a 1:1 scale device currently planned to have a 400 kilowatt capacity for use in previously mentioned wave farm to power Texal.
- Wave
This Project has the following MRE Devices
Filters:
Citation Formats
“Texel Wave Energy Pilot.” Marine Energy Projects Database: Projects, PRIMRE, United States Department of Energy, https:https://openei.org/wiki/PRIMRE/Databases/Projects_Database/Projects/Texel_Wave_Energy_Pilot. Accessed <day> <monthRoman> <year>.
Marine Energy Projects Database: Projects. <year>. "Texel Wave Energy Pilot." Accessed <monthRoman> <day>, <year>. https:https://openei.org/wiki/PRIMRE/Databases/Projects_Database/Projects/Texel_Wave_Energy_Pilot.