North Steens 230kV Transmission
NEPA Document Collection for: North Steens 230kV Transmission
EIS
North Steens 230-kV Transmission Project EIS
Proposed Action
The North Steens 230-kV Transmission Line Project would transmit electrical power from the proposed Echanis Project (a 104-megawatt wind energy facility near Diamond, Oregon) to an existing 115-kV transmission line near Diamond Junction, Oregon operated by Harney Electric Cooperative (HEC). The North Steens Transmission Line would cross approximately 18.70 miles of private land, 8.85 miles of land administered by the BLM (Burns District Office), and 1.32 miles of the Malheur National Wildlife Refuge (MNWR) managed by the U.S. Fish and Wildlife Service (USFWS). The new transmission line would be constructed on double-circuit steel-pole towers placed within a new 150-foot wide right-of-way (ROW).
Full build out of the Project would occur in phases. During Phase I, a single circuit (three conductors) would be installed on one side of each pole and operated at 115-kV. During Phase II, a second circuit (three conductors) would be installed on the other side of each pole and operated at 230-kV. During Phase III, the operational voltage of the Phase I transmission line would be increased to 230-kV. All of the Project components installed with the first circuit, including poles, conductors, insulators, ROW width, pole spacing, and so forth would meet 230-kV design standards. The second circuit would be added in the future, if needed, to serve other wind energy projects developed in the area.
Renewable energy generated at the Echanis Project would be transmitted and distributed to the regional power market via the North Steens Transmission Line and the regional electrical transmission grid. The Applicant anticipates that the new transmission line and ancillary facilities could be used to transmit electric power from other potential wind energy projects developed in the Harney County area.
Current Status
On March 16, 2012, the BLM issued a Right-of-Way (under Title V of the Federal Land Policy Management Act) to Echanis, LLC (the project proponent) for the North Steens Transmission Line Project. The BLM and Echanis, LLC then worked together to ensure the 10 plans necessary for the next step in the process - a Notice to Proceed authority given by the BLM - met the intent of the project's Record of Decision. On May 21, 2012 the BLM issued a limited Notice to Proceed that allows the project proponent to move forward with non-ground breaking activities in preparation for construction. On February 22, 2013, the BLM revoked the limited Notice to Proceed and refunded the bond to the project proponent. Due to litigation, the project has been on hold for nearly 2 years. As a result, the BLM will have to recalculate the bond and issue a new Notice to Proceed prior to construction. District Court Judge Mosman found for BLM on all counts in the District Court Decision issued September 11, 2013. The appellants appealed the decision to the 9th Circuit Court of Appeals.
Conditions of Approval
The decision is conditioned on implementation of best management practices (BMP)s and Project Design Features (PDF)s as provided in the applicant’s Plan of Development (POD) and mitigation measures applicable to the Transmission Project as described under Alternative C – North Route, as well as incorporation of applicable elements of the Echanis Wind Power Project: Principles and Standards for Development of a Habitat Mitigation Plan (HMP) (Mitigation Principles and Standards for MPS), Echanis’ HMP and Echanis’ Eagle Conservation Plan and Bird and Bat Conservation Strategies for the Echanis Wind Energy Facility and the North Transmission Route Alternative (more commonly referred to as an Avian and Bat Protection Plan/Eagle Conservation Plan or ABPP/ECP). These applicable measures have been developed into specific, enforceable terms, conditions, and stipulations will be incorporated into the authorized right-of-way ROW grants.
The grants will include a stipulation that Echanis implement a construction compliance and monitoring plan to ensure construction activities on BLM-administered lands satisfy the requirements of the ROW grants, PDFs, BMPs, as well as any conditions required through any of the Transmission Project’s Federal, state, or local permits for actions related to the Transmission Project. The grants will also require Echanis to retain copies of all applicable construction permits onsite and to educate construction personnel on avoidance of sensitive areas, compliance and monitoring requirements. Upon identification of a non-compliance issue on public land, or discovery of archaeological resources, Echanis will notify the BLM immediately and work with the responsible contractors or workers to correct the problem. Echanis will provide monthly written reports to the BLM documenting compliance reporting any environmental problems as well as corrective actions taken to resolve these problems. Several of the mitigation plans and agreements referenced in the FEIS have specific monitoring requirements and protocols which specify both construction and long-term monitoring. Plan provisions applicable to the Transmission Project including applicable monitoring requirements are being made a condition of the ROW grants. Mitigation plans and agreements which contain specific monitoring requirements include:
- ABPP/ECP for the Echanis Wind Energy Facility and the Selected Alternative
- Habitat Mitigation Plan
- Weed Management and Control Plan
- Revegetation Plan
- Programmatic Agreement relative to Section 106 of the NHPA
BMPs, PDFs, applicable mitigation measures, monitoring provisions, and stipulations are included in the FEIS, ROD, and ROW grants.
Data Completion Notes
BLM Project Website: http://www.blm.gov/or/districts/burns/plans/steen_trans/ Applicant Website: http://columbiaenergypartners.com/about/press/north-steens-transmission-line-eis-key-facts/
Documents
EA/EIS Report:
Resource Analysis
Resource | Not Present |
Present, Not Affected |
Present, Potentially Affected |
Not Indicated |
Comment | Applicant Proposed Mitigation |
Agency Imposed Mitigation |
---|
Access and Transportation |
|
CloseApplicant Proposed Mitigation Measures:
|
Cultural Resources |
|
CloseApplicant Proposed Mitigation Measures:
|
Fire Resources |
|
CloseApplicant Proposed Mitigation Measures:
|
Invasive, Nonnative Species |
|
CloseApplicant Proposed Mitigation Measures:
The plan will specify appropriate revegetation timing, techniques, and seed mix(es). Adherence to this plan will also help limit the spread and establishment of noxious weeds. Certified “noxious weed-free” seed must be used on all areas to be restored. Other construction material, such as fill, shall also be free of noxious weed seed.
|
Noise |
|
CloseApplicant Proposed Mitigation Measures:
|
Soils |
|
CloseApplicant Proposed Mitigation Measures:
|
Special Status Species |
|
CloseApplicant Proposed Mitigation Measures:
|
Vegetation |
|
CloseApplicant Proposed Mitigation Measures:
|
Visual Resources |
|
CloseApplicant Proposed Mitigation Measures:
|
Wastes Hazardous or Solid |
|
CloseApplicant Proposed Mitigation Measures:
|
Water Quality |
|
CloseApplicant Proposed Mitigation Measures:
Section 3.17.2 Public Health and Safety: Hazardous Materials for further details.
|
Wetlands and Riparian Zones |
|
CloseApplicant Proposed Mitigation Measures:
|
Wildlife Resources |
|
CloseApplicant Proposed Mitigation Measures:
|