California CAISO Interconnection Request (8-CA-b)

Information current as of 2024
In California, a developer may need to submit an interconnection request to the California Independent System Operator (CAISO) to connect a generating facility to the California ISO grid. The facility may use either the traditional Queue Cluster Study Process or the Fast Track Process to qualify for interconnection. Each process has eligibility requirements that the facility must meet in order to apply using that process. The specific requirements and a detailed explanation of each study process are available in the Generation Interconnection and Deliverability Allocation Procedures.


Hydropower

All generating facilities seeking interconnection with the Distribution Providers Transmission System must apply with CAISO for interconnection and are subject to the CAISO tariff. Those generating facilities, subject to Federal Energy Regulatory Commission (FERC) jurisdiction must apply under a Distribution Provider’s Wholesale Distribution Tariff (WDT) regardless of whether they interconnect to a Distribution Provider’s Distribution or Transmission System. Cal. Pub. Util. Comm'n. R. 21; Cal. Pub. Util. Comm'n. Decision 12-09-018, p. A-1-A-2. In 2012, the California Public Utility Commission adopted a settlement agreement revising electric tariff Rule 21, this settlement agreement added language to state clearly when an applicant may apply for interconnection pursuant to Rule 21 procedures.



CAISO Interconnection Request Process


8-CA-b.1 – Is the Project Eligible for the Fast Track Process?

In order to be eligible for the Fast Track Process, the project must be a certified small generating facility that does not have a generating capacity of more than 5 MW and is applying for energy-only deliverability status, which is defined as a condition elected by an interconnection customer (IC) for a large generating facility interconnected with the CAISO controlled grid that makes the IC responsible only for the costs of reliability network upgrades and not the cost of delivery network upgrades. The IC must submit a completed interconnection request (IR), a $500 processing fee, a study deposit of $1,000, and a demonstration of site exclusivity. The IC may request to be evaluated under the Fast Track Process at any time. If the project is Fast Track Eligible, the facility must pass the required screening process to be approved for interconnection to the grid.

Generation Interconnection and Deliverability Allocation Procedures, section 5.


8-CA-b.2 to 8-CA-b.4– Conduct Fast Track Screening Process

If the project qualifies for the Fast Track Process it must pass the screening process in order to be approved for interconnection to the CAISO grid. The CAISO will review the proposed project to determine that:

  • For interconnection of a proposed facility to a radial transmission circuit, the aggregated generation on the circuit, including the proposed generating facility, does not exceed 15 percent of the line section annual peak load as most recently measured at the substation. A line section is the portion of a participating transmission owner's (TO) electric system connected to a customer bounded by automatic sectionalizing devices or the end of the transmission line.
  • For interconnection of a proposed Generating Facility to the load side of spot network protectors, the proposed Generating Facility must utilize an inverter-based equipment package and, together with the aggregated other inverter-based generation, not exceed the smaller of five percent of a spot network's maximum load or 50 kW. A spot network is a type of distribution system found in modern commercial buildings for the purpose of providing high reliability of service to a single retail customer.
  • The proposed generating facility, together with other generation on the transmission circuit, cannot contribute more than 10 percent to the transmission circuit's maximum fault current at the point on the high voltage (primary) level nearest the proposed point of change of ownership
  • The proposed generating facility, together with other generation on the transmission circuit, must not cause any transmission protective devices and equipment (including, but not limited to, substation breakers, fuse cutouts, and line reclosers), or IC equipment on the system to exceed 87.5 percent of the short circuit interrupting capability; nor shall the interconnection proposed for a circuit that already exceeds 87.5 percent of the short circuit interrupting capability.

If the project passes all of the screens, then the IR will be approved. If the project fails one or more of the screens, but the CAISO and participating TO determine that the generating facility can still be interconnected consistent with safety, reliability, and power quality standards, then the IR will also be approved. If however, the project fails one or more of the screens and it is determined that the project cannot be interconnected according the safety, reliability, and power quality standards, the project must continue to the Cluster Queue Process.

Generation Interconnection and Deliverability Allocation Procedures, section 5.


8-CA-b.5 - Submit Interconnection Request to CAISO During a Queue Cluster Window

A developer may submit an IR for the Queue Cluster Process during one annual window, April 1st through the 31st. All IRs received during this window will be studied in the same "cluster." A "cluster" is the process of studying a group of generator IRs together, instead of individually, for the purpose of conducting interconnection system impact studies.

Many circumstances outside the Independent Service Operator's (ISO) control require consideration before connecting to the grid such as environmental requirements, land acquisition, equipment availability and permits, which leads to a lengthy application process. However, an IC’s commercial operation date (COD) cannot exceed seven years from the date on the IR, unless mutually agreed by the TO, IC, & ISO to delay beyond the this limit.

Generation Interconnection and Deliverability Allocation Procedures, section 3.3.


8-CA-b.6 - Interconnection Application, Demonstration of Site Exclusivity, System Studies

There are three items that the IC must include in its package in order to have a complete IR which are as follows:

Interconnection Study Deposit

With the exceptions of the Fast Track and the 10kW Inverter Processes the Interconnection Study Deposit is equal to $50,000 plus $1,000 per MW up to a maximum of $250,000. The calculated amount is to be rounded up to the nearest $1,000.

Each IR is studied under the direction and oversight of the ISO, although the TOs perform certain parts of the study work as noted in the Roles and Responsibilities section of the GIDAP and the pro form contractual agreement between the ISO and Participating TOs commonly known as the “Roles and Responsibilities Agreement.” The ISO will conduct or cause to be performed the required Interconnection Studies and any additional studies the ISO determines to be reasonably necessary, and will direct the applicable TO to perform portions of studies where the TO has specific and non-transferable expertise or data and can conduct the studies more efficiently and cost effectively than the ISO. GIDAP Best Management Practice

Application

The completed Application is the second of the three items that the IR must include in the package in order to have a complete IR. With the exception of the 10 kW Inverter Process, the Application will be in the form of GIDAP Appendix 1 pursuant to ISO Tariff Section 25.1, including requested deliverability status, study process (e.g. Queue Cluster, Independent, Fast Track), preferred point of interconnection, voltage level, and all other required technical data. The ISO will forward a copy of the Appendix 1 Interconnection Request to the applicable Participating TO within five Business Days of receipt.

Generation Interconnection and Deliverability Allocation Procedures, Appendix 1.

Site Exclusivity

The site exclusivity requirement must be demonstrated as part of the IC's IR package, or, in lieu of such demonstration, tender a cash-equivalent site exclusivity deposit (in addition to, and separately from the Interconnection Study Deposit). Site exclusivity demonstration is the third of the three items that the IC must include in its package in order to have a complete IR.

ICs who apply for the queue cluster study process but do not have site exclusivity at the time of the open queue cluster application window may make an additional in lieu of site exclusivity deposit (additional to their study deposit).

The IC must also provide a site exclusivity deposit which the ISO holds in an interest bearing account at a bank or financial institution designated by the ISO for return when the IC has demonstrated site exclusivity.

Generation Interconnection and Deliverability Allocation Procedures, section 3.5.

If any of the above items are not provided during the cluster application window for a cluster study, the IR will be deemed incomplete and not accepted by the ISO and there will not be an opportunity to cure these deficiencies. The ISO will follow the business practice of returning an IR to the IC without an opportunity to cure under GIDAP 3.5.2.2. The argument that a “cure” is available would result in the IC’s ability to extend the window period by resorting to “self-help” by simply providing a package that the IC knows is inadequate upon submission. Therefore, it is highly encouraged that ICs submit their entire IR packages complete in all respects in a timely manner and not wait until the last day of the open window.

GIDAP Best Management Practice, section 3.5.


8-CA-b.7 - Hold Scoping Meeting

Within five business days after the ISO notifies the IC of an IR that is complete, valid, and ready for study, the ISO must establish a date agreeable to the IC and the applicable TOs for the scoping meeting. All scoping meetings should occur no later than 60 calendar days after the close of a cluster application window, unless otherwise mutually agreed upon by the parties.

The ISO must endeavor to bring any affected system into the communications regarding the interconnection studies. The ISO will evaluate whether the IR is at or near the boundary of an affected TOs service territory or of any other affected system(s) so as to potentially affect such third parties, and, in such case, the ISO must invite the affected TOs, and/or affected system operator(s) in accordance with the GIDAP , to the scoping meeting by informing such third parties of the time and place of the scheduled scoping meeting as soon as practicable.

GIDAP Best Management Practice, p. 53.


8-CA-b.8 - Interconnection Study Agreement

Before the interconnection study process begins, ICs are required to sign an interconnection study agreement wherein the IC agrees to pay for the reasonably incurred study costs.

The timing and details of the interconnection study agreement are as follows: Within 30 Calendar Days of the close of a cluster application window, the ISO provides each IC (who has a valid IR received during the cluster application window) a pro forma Generator Interconnection Study Process Agreement in the form set forth in GIDAP Appendix 3.

Generation Interconnection and Deliverability Allocation Procedures, Appendix 3.


8-CA-b.9 - Phase I Interconnection Study Report

The Phase I Interconnection Study must:

  • Evaluate the impact of all IRs received during the applicable cluster application window on the ISO controlled grid;
  • Preliminarily identify all network upgrades needed to address the impacts on the ISO controlled grid of the IRs;
  • Preliminarily identify for each IR required interconnection facilities;
  • Assess the point of interconnection selected by each IC and potential alternatives to evaluate potential efficiencies in overall transmission upgrades costs;
  • Establish the maximum cost responsibility for network upgrades assigned to each IR in accordance with ISO tariff Appendix Y Section 6.5; and
  • Provide a good faith estimate of the cost of interconnection facilities for each IR.

Generation Interconnection and Deliverability Allocation Procedures, section 6.2.


8-CA-b.10 - Hold Results Meeting

The applicable TOs, the ISO and the IC must hold a results meeting to discuss the results of the Phase I Interconnection Study, including assigned cost responsibility, modifications, change in commercial operation date, and other possible changes addressed in GIDAP BPM Section 6.7 within 30 days of providing the Phase I Interconnection Study report to the IC,

GIDAP Best Management Practice, page 65.


8-CA-b.11 - Pre-Phase II Interconnection Agreement

The IC must submit to the ISO the completed form that is part of the generator interconnection study process agreement for queue clusters within five business days following the Phase I Interconnection Study results meeting. In this document, the IC provides critical information regarding the customer’s proposed generating facility for the purpose of scoping the Phase II Interconnection Study Work. The form is attached to GIDAP Appendix 3, the generator interconnection process agreement for queue clusters. The form is Appendix B to the agreement.

Generation Interconnection and Deliverability Allocation Procedures, Appendix B.

Through this completed form, the IC makes certain critical choices and/or affirmations about the nature of its proposed generating facility, so that the facility can be appropriately incorporated into the Phase II Interconnection Study effort.

GIDAP Best Management Practice, p, 71.


8-CA-b.12 to 8-CA-b.13 - Conduct Phase II Interconnection Study

The ISO, in coordination with the applicable TO, will conduct a Phase II Interconnection Study that will incorporate eligible IRs from the previous Phase I Interconnection Studies (or previous two Phase I Interconnection Studies for Clusters 1&2, and 3&4).

The Phase II Interconnection Study must:

  • Update, as necessary, analyses performed in the Phase I Interconnection Studies to account for the withdrawal of IRs;
  • Identify final reliability network upgrades needed to physically interconnect the generating facilities;
  • Assign responsibility for financing the identified final reliability network upgrades;
  • Identify, following coordination with the ISO’s transmission planning process, final delivery network upgrades needed to interconnect those generating facilities selecting full capacity deliverability status;
  • Assign responsibility for financing delivery network upgrades needed to interconnect those generating facilities selecting full capacity deliverability status;
  • Identify for each IR final point of interconnection and TO’s interconnection facilities;
  • Provide a +/-20% estimate for each IR of the final TO’s interconnection facilities;
  • Optimize in-service timing requirements based on operational studies in order to maximize achievement of the commercial operation dates of the generating facilities; and
  • If it is determined that the delivery network upgrades cannot be completed by the IC’s identified commercial operation date, provide that operating procedures necessary to allow the generating facility to interconnect as an energy-only resource, on an interim-only basis, will be developed and utilized until the delivery network upgrades for the generating facility are completed and placed into service.

Generation Interconnection and Deliverability Allocation Procedures, section 8.

Phase II Interconnection Study must be completed within 150 days following the posting of the initial Interconnection financial security posting if the IC meets the following criteria:

  • the IR was not grouped with other IRs during the Phase I Interconnection Study or was identified as interconnecting to a point of available transmission in the Phase I Interconnection Study; and
  • the IC demonstrates the general Phase II Interconnection Study timeline is not sufficient to accommodate the COD for the large generating facility.

Generation Interconnection and Deliverability Allocation Procedures, section 8.5.


8-CA-b.14 - Hold Results Meeting

The TO, ISO, and the IC will participate in a Phase II Results Meeting meet to discuss the results, including selection of the final commercial operation date within 30 days of providing final Phase II study report to the IC. Note the ISO’s current practice is to incorporate the time frame for completion of the transmission build out when determining the COD.

Generation Interconnection and Deliverability Allocation Procedures, section 8.7.


8-CA-b.15 - Generator Interconnection Agreement

No more than 90 days after ISO provides a final Phase II Interconnection Study report or a facility study report (or system impact study report if the facilities study is waived) for negotiation of the Generator Interconnection Agreement (GIA), unless otherwise agreed by the parties.

If the IC executes the final GIA, the applicable TO(s), ISO and the IC must perform their respective obligations in accordance with the terms of the GIA, subject to modification by Federal Energy Regulatory Commission.

Generation Interconnection and Deliverability Allocation Procedures, section 13.