RAPID/Roadmap/3-QC-b

From Open Energy Information

< RAPID‎ | Roadmap

RAPIDRegulatory and Permitting Information Desktop Toolkit
My Projects

Quebec Crown Land Right-of-Way (3-QC-b)

Information current as of 2019
In Quebec, there is not a specific provincial land right-of-way approval, however a developer must ensure that the bulk transmission project complies with provincial and local land use plans. The Quebec Department of Energy and Natural Resources manages provincial public land in Quebec.



Crown Land Right-of-Way Process


3-QC-b.1 – Contact Quebec Department of Energy and Natural Resources

The developer should contact the Quebec Department of Energy and Natural Resources to ensure the proposed project is in compliance with any provincial land access requirements.

3-QC-b.2 – Review Provincial and Local Land Use Plans

A developer should review all applicable provincial and local land use plans where the proposed project will be located to ensure compliance. R.S.Q. 1999, c. T-8.1 s. 21. For more information, see: