RAPID/Roadmap/3-ON-c
Ontario Provincial Highway Right-of-Way Overview (3-ON-c)
Provincial Highway Right-of-Way Overview Process
3-ON-c.1 – Contact Local Government
A developer should also contact the local municipality or governing body for any additional permits that may be required.
3-ON-c.2 to 3-ON-c.4 – Will the Project Encroach Upon, Under, or Within a Provincial Highway Right-of-Way?
A developer may need an Provinicial Highway Encroachment Permit if the project will encroach upon, under, or within a provincial highway right-of-way. Ontario Ministry of Transportation – Encroachment Permit Webpage. If a developer may need an Encroachment Permit, see:
Provinical Highway Encroachment Permit:
3- ON-d
3-ON-c.5 to 3-ON-c.7 – Will the Project Require Constructing a Commercial Structure Near a Provincial Highway Right-of-Way?
A developer may need a Provincial Highway Building and Land Use Permit if the project involves constructing a commercial structure close or adjacent to a provincial highway. s 31(1)(b); Ontario Ministry of Transportation – Building and Land Use Permit Webpage. A power and/or transmission line is considered a “commercial structure.” Ontario Ministry of Transportation – Building and Land Use Policy Manual. If a developer may need a Building and Land Use Permit, see:
Agencies
Contact Information
Suggest a contact using the Feedback button above.Suggest edits using the Feedback button above.
References
Edit
Ontario Ministry of Transportation
Ministers Office
1-800-268-4686
Visit Website