Oklahoma State Land Right-of-Way (3-OK-b)
State Land Right-of-Way Process
3-OK-b.1 — Application for State Land Easement
The developer must submit a State Land Easement Application (Application) to the Oklahoma Commissioners of the Land Office (the Commissioners) to construct powerlines or roads on Commissioners designated state land. State Land Easement Process and Procedures. The Application must include a survey with centerline and a legal description of the land in question. Oklahoma Commissioners of the Land Office — Easements Webpage. The Application must also include three copies of the certified plat/survey, and a non-refundable Application fee and deposit to secure a possible State Land Easement - Temporary Construction Permit. State Land Easement Process and Procedures; State Land Easement Application.
3-OK-b.2 to 3-OK-b.3 — Review Application for Completeness
After receiving the Application, the Commissioners review the Application for administrative and technical completeness. If the Commissioners have any questions regarding the application, they will contact the developer for additional information. State Land Easement Process and Procedures.
3-OK-b.4 to 3-OK-b.6 — Review State Land Easement Application for Approval
If the Application is complete the Commissioners review the Application and make a decision on granting or rejecting the Application State Land Easement Process and Procedures. If the Commissioners choose to grant the State Land Easement, then the Commissioners will issue a State Land Easement - Temporary Construction Permit. State Land Easement Application.
3-OK-b.7 — Appraise the Land
The Commissioners must then have the state land appraised by the appropriate Real Estate Management Specialist in order to determine the state lands value and the final amount due to secure the State Land Easement. State Land Easement Process and Procedures.
3-OK-b.8 — Pay Amount Due
The developer must pay the valuation given to the state land by the Real Estate Management Specialist in order to secure the State Land Easement. State Land Easement Process and Procedures.
3-OK-b.9 — State Land Easement
The Commissioners may issue a State Land Easement after approving the Application and once the developer pays the amount due. The Commissioners issues State Land Easements for a maximum of 20 years to non-state governmental entities. The developer may apply for renewal of a State Land Easement in 20 years by submitting a State Land Easement Application 20 Year Renewal to the Commissioners’ Office. State Land Easement Application 20 Year Renewal.
3-OK-b.10 — Appeal Decision (Optional)
A developer may appeal the Commissioners’ decision for judicial review under Ok. Stat. Ann. §75-318.
Contact Information
Suggest a contact using the Feedback button above.Suggest edits using the Feedback button above.
Regulations
References
- Oklahoma Commissioners of Land Office – State Land Easement Application
- Oklahoma Commissioners of Land Office – State Land Easement Process and Procedures
- Oklahoma Commissioners of the Land Office — Easements Webpage
- Oklahoma Commissioners of the Land Office — Real Estate Management Specialists
- State Land Easement Application 20 Year Renewal
- Oklahoma Commissioners of the Land Office — Rules & Regulations webpage.