RAPID/Roadmap/3-NE-b
Nebraska State Land Right-of-Way (3-NE-b)
State Land Right-of-Way Process
3-NE-b.1 – Contact State Agency with Jurisdiction Over Land
The developer should contact the appropriate state agency with jurisdiction over the state land in question about obtaining either a Temporary or Permanent Utility Easement.
3-NE-b.2 – Submit Utility Easement Request
After complying with the appropriate state agency Utility Easement request process, the state agency may then submit a Utility Easement request to the Nebraska Vacant Building and Excess Land Committee (“Committee”) for approval. The applicable state agency must submit a Utility Easement request to the Committee Property Manager on a Nebraska Vacant Building and Excess Land Committee Request Form (“Request Form”) via e-mail, inter-office mail, or fax, along with any documents related to the easement request. Nebraska Vacant Building and Excess Land Committee: Frequently Asked Question Website.
3-NE-b.3 – Review Utility Easement Request
Upon receipt of a fully executed Request Form, the Committee Property Manager will research the request and request additional information if needed. Nebraska Vacant Building and Excess Land Committee: Frequently Asked Question Website.
3-NE-b.4 – Perform Survey (If Applicable)
The Committee Property Manager may also require the performance of a survey regarding the Utility Easement request. Nebraska Vacant Building and Excess Land Committee: Frequently Asked Question Website.
3-NE-b.5 to 3-NE-b.6 – Prepare Recommendation for Committee Decision
The Committee Property Manager will place the Utility Easement request on the next meeting agenda and prepare a recommendation for the Committee to consider the request at the Committee meeting. Nebraska Vacant Building and Excess Land Committee: Frequently Asked Question Website. After reviewing the Utility Easement request information, the Committee will grant, deny or table the request. The Committee may approve a Utility Easement by majority vote. Nebraska Vacant Building and Excess Land Committee: Frequently Asked Question Website.
3-NE-b.7 – Submit Record Fee
If the request is approved, the requestor will send or deliver a check for the amount of the recordation fee to the Nebraska Department of Administrative Services, Central Services. Nebraska Vacant Building and Excess Land Committee: Frequently Asked Question Website.
3-NE-b.8 – Utility Easement
The Committee must certify the approval of a Utility Easement to the Director of Administrative Services who must execute the instrument necessary to grant the easement. Nebraska Vacant Building and Excess Land Committee: Frequently Asked Question Website.
3-NE-b.9 – Record Utility Easement
Upon execution, the requestor is responsible for the recordation of the agreement in the applicable County Register of Deeds office and for sending a copy of the recorded document to the Committee Property Manager. Nebraska Vacant Building and Excess Land Committee: Frequently Asked Question Website.
3-NE-b.10 – Appeal Decision (If Applicable)
Any aggrieved party by a final state agency decision is entitled to judicial review under the Administrative Procedure Act. 84 N.R.S. §§ 917, 919.