Colorado Electric Cooperatives - Interconnection Standards (Colorado)

From Open Energy Information


Last modified on February 12, 2015.

Rules Regulations Policies Program

Place Colorado
Name Colorado Electric Cooperatives - Interconnection Standards
Incentive Type Interconnection
Applicable Sector Commercial, Residential
Eligible Technologies Photovoltaics, Landfill Gas, Wind, Biomass, Hydroelectric, Municipal Solid Waste
Active Incentive No
Implementing Sector Utility
Energy Category Renewable Energy Incentive Programs
Applicable Utilities Varies by utility






External Disconnect Switch Yes


Insurance Requirements No


Net Metering Required Varies by utility





Standard Agreement Varies by utility
System Capacity Limit Varies by utility








Date added to DSIRE 2004-03-30
Last DSIRE Review 2007-06-20


References DSIRE[1]


Summary

Colorado enacted legislation in 2002 that implemented certain interconnection standards and metering requirements for the state's electric cooperatives. According to the statute, standby charges and interconnection charges are specifically authorized, and customers must pay all costs for additional metering. Safety equipment includes a requirement for an external disconnect switch. Customer equipment must meet IEEE, UL and National Electric Code (NEC) requirements, and any other applicable regulations or standards. Cooperative utilities must approve every eligible interconnection.

Although the statute requires the state's electric cooperatives to offer "net metering," the term "net metering" is a misnomer in this case. Under the law, customers receive a lower rate -- the utility's avoided-cost rate -- for all electricity generated, while customers must pay the full retail rate for all electricity they purchase from utilities. This practice, commonly known as "dual metering," is much less favorable to customer-generators than "true" net metering. At least four electric cooperatives (Delta-Montrose Electric Association, Gunnison County Electric Association, La Plata Electric Association and Empire Electric Association) and two municipal utilities (Fort Collins Utilities and Holy Cross Electric) offer "true" net metering.

In November 2004, Colorado voters approved Amendment 37, a ballot initiative that created a renewables portfolio standard (RPS) that applies to all of the state's utilities. Subsequently, in December 2005, the Colorado Public Utilities Commission (PUC) adopted statewide interconnection standards and net-metering rules. These rules apply to utilities serving at least 40,000 Colorado customers; municipal utilities and cooperative utilities with fewer than 40,000 customers may vote to opt out of the requirements of Amendment 37.


Authorities (Please contact the if there are any file problems.)

Authority 1: C.R.S. 40-9.5-301 et seq.
Date Effective 2002-07-01
Date Enacted 2002

















  • Incentive and policy data are reviewed and approved by the N.C. Solar Center's DSIRE project staff.[1]

References

  1. 1.0 1.1  "Database of State Incentives for Renewables and Efficiency (DSIRE)"