Sigurd Red Butte No2
NEPA Document Collection for: Sigurd Red Butte No2
EIS
Sigurd to Red Butte No. 2 345kV Transmission Project
Proposed Action
BLM: The BLM is proposing to grant the Proponent right-of-way across the federal lands they administer to accommodate the Proponent’s proposed Project for a lease term of 30 years with right to renew.
The Proponent’s Proposed Action is to construct, operate, and maintain a single-circuit 345kV transmission line from the existing Sigurd Substation, located north of Richfield, in Sevier County, Utah, to the existing Red Butte Substation, located west of Central, in Washington County, Utah. Permanent facilities would include: -A single-circuit, alternating current 345kV overhead transmission line (including structures, shield wires, conductors, and insulators) between the Sigurd Substation and Red Butte Substation -Communication regeneration stations associated with the transmission line -Access roads to the 345kV transmission line structures where needed and where there is no existing access -New substation equipment at terminus points to interconnect the Project with the existing Sigurd and Red Butte substations
The Proposed Action and Project description are presented in detail in Chapter 2, Sections 2.2 and 2.3, of the Final Environmental Impact Statement (EIS).
USFS: The USFS is proposing to authorize the Proponent to cross the federal lands they administer to accommodate the Proponent’s proposed Project for a period of 30 years with right to renewal. -The Proponent’s Proposed Action is to construct, operate, and maintain a single-circuit 345kV transmission line from the existing Sigurd Substation, located north of Richfield, in Sevier County, Utah, to the existing Red Butte Substation, located west of Central, in Washington County, Utah. -A single-circuit, alternating current 345kV overhead transmission line (including structures, shield wires, conductors, and insulators) between the Sigurd Substation and Red Butte Substation Communication regeneration stations associated with the transmission line -Access roads to the 345kV transmission line structures where needed and where there is no existing access -New substation equipment at terminus points to interconnect the Project with the existing Sigurd and Red Butte substations -The Proposed Action and Project description are presented in detail in Chapter 2, Sections 2.2 and 2.3, of the Final Environmental Impact Statement (EIS).
Conditions of Approval
BLM: This Project includes the following measures, terms, and conditions: -Monitoring and mitigation measures outlined in Chapter 3 and Appendix F of the Final EIS and the POD (refer to Appendix B of this ROD); -Terms and conditions in the Programmatic Agreement that are provided in Appendix 3 of the Programmatic Agreement; -Mitigation measures that would be implemented to eliminate or minimize impacts on greater sage-grouse as outlined in Appendix F of the Final EIS and included in the approved Compensatory Mitigation Plan for Greater Sage-Grouse (Rocky Mountain Power 2012); and -Standard terms, conditions, and stipulations (43 CFR 2800).
Before BLM will issue a notice to proceed with construction, the Proponent must post a financial security (such as a surety bond, letter of credit, etc.) with the BLM in an amount sufficient to cover all post-fieldwork costs associated with implementing the Historic Properties Treatment Plan (HPTP), or other mitigation activities, to be required by the Proponent when they contract for services in support of the Programmatic Agreement and for reclamation requirements and activities.
The Proponent will provide for an environmental compliance inspection contractor (CIC), to be approved by the BLM and USFS, to represent the BLM and USFS during the onstruction and reclamation phases of the Project. The CIC will report directly to the BLM. The primary role and responsibility of the CIC is to ensure compliance with all terms, conditions, and stipulations of the right-of-way grant, the POD, and other permits, approvals and regulatory requirements, as described in Section 1.9 of the Final EIS and Section 1.6 of the POD (refer to Appendix B of this ROD). Additionally, the CIC shall follow the Environmental Compliance Management Plan, included as Appendix A6 of the POD.
The Proponent also will be responsible for monitoring the reclamation of the transmission line, temporary access roads, and ancillary facilities, as described in Appendix B14 (Reclamation, Revegetation, and Monitoring Framework Plan), and for compliance with Appendix B10 Noxious Weed Management Plan) of the POD.
USFS: As required by the standard terms of the special-use authorization, initiation of construction is conditioned upon final USFS approval of the POD.
As a requirement of the standard terms of the special-use permit authorization and the POD, the Proponent will provide for an environmental compliance inspection contractor (CIC), to be approved by the BLM, as lead federal agency, and USFS, to represent the BLM and USFS during the construction and reclamation phases of the Project. The CIC will report directly to the BLM, as lead federal agency, in coordination with USFS. The primary role and responsibility of the CIC is to ensure compliance with all terms, conditions, and stipulations of special-use authorization, the POD, and other permits, approvals and regulatory requirements, as described in Section 1.9 of the Final EIS and Section 1.6 of the POD (refer to Appendix B of this Record of Decision). Additionally, the CIC shall follow the Environmental Compliance Management Plan, included as Appendix A6 of the POD. The Proponent also will be responsible for monitoring the reclamation of the transmission line, temporary access roads, and ancillary facilities, as described in Appendix B14 (Reclamation, Revegetation, and Monitoring Framework Plan), and for compliance with Appendix B10 Noxious Weed Management Plan) of the POD.
Data Completion Notes
Preliminary SF299, POD, Scoping Document, and other important project documents located here: http://www.blm.gov/ut/st/en/fo/cedar_city/planning/sigurd_to_red_butte.html
Documents
Application:
Resource Analysis
Resource | Not Present |
Present, Not Affected |
Present, Potentially Affected |
Not Indicated |
Comment | Applicant Proposed Mitigation |
Agency Imposed Mitigation |
---|
Cultural Resources |
|
CloseDesign Features of the Proposed Action for Environmental Protection:
|
CloseDesign Features of the Proposed Action for Environmental Protection:
|
Fire Resources |
|
CloseDesign Features of the Proposed Action for Environmental Protection:
|
Geology and Minerals |
|
CloseDesign Features of the Proposed Action for Environmental Protection:
All areas on lands administered by Bureau of Land Management (BLM) or U.S. Forest Service (USFS) disturbed as a part of the construction and/or maintenance of the proposed transmission line would be reseeded with a seed mixture appropriate for those areas. The BLM or USFS would prescribe a seed mixture that fits each range site. Seeding methods would typically include drill seeding, where practicable; however, the BLM or USFS may recommend broadcast seeding as an alternative method in some cases. Drill seeding for all Project areas outside the jurisdiction of the BLM Cedar City Field Office would be performed during September 1 through December 15 to maximize the chance of success. Within the jurisdiction of the BLM Cedar City Field office, drill seeding would be performed October 15 through December 15. Where broadcast seeding is implemented, seed would be applied at 1.5 to 2 times the rate of drill seeding application, and the seed would be covered by a method such as harrowing or raking. A Reclamation, Revegetation, and Monitoring Framework Plan identifying reclamation stipulations would be developed and incorporated in the Plan of Development (POD), which would be approved by the BLM and USFS prior to the issuance of a right-of-way grant or special-use authorization, respectively.
|
CloseDesign Features of the Proposed Action for Environmental Protection:
|
Lands and Realty |
|
CloseDesign Features of the Proposed Action for Environmental Protection:
|
CloseDesign Features of the Proposed Action for Environmental Protection:
|
Migratory Birds |
|
CloseDesign Features of the Proposed Action for Environmental Protection:
|
CloseDesign Features of the Proposed Action for Environmental Protection:
‘’Migratory Birds’’
|
Noise |
|
CloseDesign Features of the Proposed Action for Environmental Protection:
|
Paleontological Resources |
|
CloseDesign Features of the Proposed Action for Environmental Protection:
|
CloseDesign Features of the Proposed Action for Environmental Protection:
|
Public Health and Safety |
|
CloseDesign Features of the Proposed Action for Environmental Protection:
|
Soils |
|
CloseDesign Features of the Proposed Action for Environmental Protection:
|
CloseDesign Features of the Proposed Action for Environmental Protection:
|
Vegetation |
|
CloseDesign Features of the Proposed Action for Environmental Protection:
All areas on lands administered by Bureau of Land Management (BLM) or U.S. Forest Service (USFS) disturbed as a part of the construction and/or maintenance of the proposed transmission line would be reseeded with a seed mixture appropriate for those areas. The BLM or USFS would prescribe a seed mixture that fits each range site. Seeding methods would typically include drill seeding, where practicable; however, the BLM or USFS may recommend broadcast seeding as an alternative method in some cases. Drill seeding for all Project areas outside the jurisdiction of the BLM Cedar City Field Office would be performed during September 1 through December 15 to maximize the chance of success. Within the jurisdiction of the BLM Cedar City Field office, drill seeding would be performed October 15 through December 15. Where broadcast seeding is implemented, seed would be applied at 1.5 to 2 times the rate of drill seeding application, and the seed would be covered by a method such as harrowing or raking. A Reclamation, Revegetation, and Monitoring Framework Plan identifying reclamation stipulations would be developed and incorporated in the Plan of Development (POD), which would be approved by the BLM and USFS prior to the issuance of a right-of-way grant or special-use authorization, respectively.
USFS, U.S. Fish and Wildlife Service, Utah Division of Wildlife Resources, etc.). This would entail conducting surveys for plant and wildlife species of concern along the proposed transmission line route and associated facilities (e.g., access and spur roads, staging areas, etc.) as agreed on by the agencies. In cases where such species are identified, appropriate action would be taken to avoid adverse impacts on the species and its habitat. These actions may include altering the placement of roads or towers, where practicable as approved by the landowner and compliance inspection contractor, as well as monitoring activities, implementation of Project speed limits, and other restrictions.
|
CloseDesign Features of the Proposed Action for Environmental Protection:
|
Visual Resources |
|
CloseDesign Features of the Proposed Action for Environmental Protection:
All areas on lands administered by Bureau of Land Management (BLM) or U.S. Forest Service (USFS) disturbed as a part of the construction and/or maintenance of the proposed transmission line would be reseeded with a seed mixture appropriate for those areas. The BLM or USFS would prescribe a seed mixture that fits each range site. Seeding methods would typically include drill seeding, where practicable; however, the BLM or USFS may recommend broadcast seeding as an alternative method in some cases. Drill seeding for all Project areas outside the jurisdiction of the BLM Cedar City Field Office would be performed during September 1 through December 15 to maximize the chance of success. Within the jurisdiction of the BLM Cedar City Field office, drill seeding would be performed October 15 through December 15. Where broadcast seeding is implemented, seed would be applied at 1.5 to 2 times the rate of drill seeding application, and the seed would be covered by a method such as harrowing or raking. A Reclamation, Revegetation, and Monitoring Framework Plan identifying reclamation stipulations would be developed and incorporated in the Plan of Development (POD), which would be approved by the BLM and USFS prior to the issuance of a right-of-way grant or special-use authorization, respectively.
|
CloseDesign Features of the Proposed Action for Environmental Protection:
9*Maximum Span at Crossings: At highway, canyon, and trail crossings, towers would be placed at the maximum feasible distance from the crossing within limits of standard tower design and in conformance with engineering and PacifiCorp requirements to reduce visual impacts and potential impacts on recreation values and to increase safety at these locations.
|
Wetlands and Riparian Zones |
|
CloseDesign Features of the Proposed Action for Environmental Protection:
26*The spatial limits of construction activities would be predetermined with activity restricted to and confined within those limits. No paint or permanent discoloring agents indicating survey or construction limits would be applied to rocks, vegetation, structures, fences, etc.
|
CloseDesign Features of the Proposed Action for Environmental Protection:
|
Water Quality |
|
CloseDesign Features of the Proposed Action for Environmental Protection:
|
CloseDesign Features of the Proposed Action for Environmental Protection:
|
Wildlife Resources |
|
CloseDesign Features of the Proposed Action for Environmental Protection:
2011). New substations or modified portions of the existing substations must incorporate animal protections in accordance with PacifiCorp standards.
|
CloseDesign Features of the Proposed Action for Environmental Protection:
‘’Big Game’’
‘’Southwestern willow flycatcher’’
‘’Utah prairie dog’’
‘’Greater sage-grouse’’
|