Soils
"NEPA_Resource_Analysis" is not in the list of possible values (Not Present, Present, Not Affected, Present, Potentially Affected, Not Indicated) for this property. |
|
|
|
|
Also includes Vegetation measures
|
|
Close
- During initial well pad and road construction and prior to completion of the final well on the well pad, pre-interim reclamation stormwater management actions will be taken to ensure disturbed areas are quickly stabilized to control surface water flow and to protect both the disturbed and adjacent areas from erosion and siltation. This may involve construction and maintenance of temporary silt ponds, silt fences, berms, ditches, and mulching. (ACLLC)
- Prior to rigging up, a berm at least one-foot high will be constructed around the perimeter of the pad to prevent escape of spilled fluids or rainfall collected on the location. This berm will be maintained during the drilling phase of the well. The need for the berm will be reassessed upon completion of the well and production is established. (BLM)
- Any water bars built during construction or reclamation to divert water from ditches or roads will be placed as follows (BLM):
Grade Spacing
2% Every 200 feet
2-4% Every 100 feet
4-5% Every 75 feet
5+% Every 50 feet
- Drainage control shall be ensured over the entire road through the use of borrow ditches, outsloping, insloping, natural rolling topography, lead-off (turnout) ditches, culverts, and/or drainage dips. (BLM)
- All lead-off ditches (turnouts) shall be graded to drain water with a one percent minimum to three percent maximum ditch slope. The spacing interval for lead-off ditches shall be determined according to the following table, but may be amended depending upon existing soil types and centerline road slope (in %):
SPACING INTERVAL FOR TURNOUT DITCHES
Percent Slope Spacing Interval
0% - 4% 400’ – 150’
4% – 6% 250’ – 125’
6% – 8% 200’ – 100’
8% - 10% 150’ - 75’
A typical lead-off ditch has a minimum depth of one foot below and a berm 6 inches above natural ground level. The berm will be on the down-slope side of the lead-off ditch. The ditch end will tie into vegetation whenever possible. (BLM)
- Road and well production equipment will be placed on location so as to permit maximum interim reclamation of disturbed areas. If equipment is found to interfere with the proper interim reclamation of disturbed areas, the equipment will be moved so proper recontouring and revegetation can occur. (ACLLC)
- Topsoil will be evenly spread and aggressively revegetated over the entire disturbed area not needed for all-weather operations including road cuts and fills and to within a few feet of the wellhead/pump, unless an all-weather, surfaced, access route or small “teardrop” turnaround is needed on the well pad. (ACLLC)
- In order to inspect and operate the well or complete workover operations, it may be necessary to drive, park, and operate equipment on restored, interim vegetation within the previously disturbed area. Damage to soils and interim vegetation will be repaired and reclaimed following use. To prevent soil compaction, under some situations, such as the presence of moist, clay soils, the vegetation and topsoil will be removed prior to workover operations and restored and reclaimed following workover operations. (ACLLC)
- Vegetation removal and the degree of surface disturbance will be minimized wherever possible. (ACLLC)
- Operations will disturb the minimum amount of surface area necessary to conduct safe and efficient operations. When possible, equipment will be stored and operated on top of vegetated ground to minimize surface disturbance. (ACLLC)
- Excess soil will be stripped and stockpiled around the perimeter of the well location to control run-on and run-off, and to make redistribution of topsoil more efficient during interim reclamation. Stockpiled topsoil may include vegetative material. Topsoil will be clearly segregated and stored separately from subsoils. (ACLLC)
- Earthwork for interim and final reclamation will be completed within 6 months of well completion or plugging unless a delay is approved in writing by the BLM AO. (ACLLC)
- If, upon completion of well drilling and well testing at a site, no geothermal resources have been found viable and no further exploration is to be pursued, roads and pads would be restored to their original condition by contouring and revegetating. (ACLLC and BLM)
- If the use of topsoil for reclamation is delayed for more than 6 months from completion or plugging of the well, the stockpiles will be reseeded to retain soil quality and hinder erosion. Fall seeding is preferred and will be conducted after September 15 and prior to ground freezing. Spring seeding will be conducted after the frost leaves the ground and no later than May 15. The seed mix recommended by the BLM in this section (COA 19), less the Wyoming big sagebrush should be used for this purpose. (BLM)
- Salvaging and spreading topsoil will not be performed when the ground or topsoil is frozen or too wet to adequately support construction equipment. If such equipment creates ruts in excess of four (4) inches deep, the soil will be deemed too wet and activities will cease until the site dries out. (ACLLC)
- No major depressions will be left that would trap water and cause ponding. (ACLLC)
- Initial seedbed preparation would consist of recontouring the well pads to the appropriate interim or final reclamation standard. All compacted areas to be seeded will be ripped to a minimum depth of 18 inches with a minimum furrow spacing of 2 feet, followed by recontouring the surface and then evenly spreading the topsoil. Prior to seeding, the seedbed will be scarified and left with a rough surface. (ACLLC)
- If broadcast seeding is to be used, final seedbed preparation will consist of contour cultivating to a depth of 4 to 6 inches within 24 hours prior to seeding and dozer tracking or another imprinting method will be used in order to loosen up the soil and create seed germination micro-sites. (ACLLC)
- Seeding will be conducted no more than 24 hours following completion of final seedbed preparation. A certified weed-free seed mix designed by BLM, as identified below, to meet reclamation standards will be used to revegetate all disturbed areas. (ACLLC)
Species Pounds/Acre – Pure Live Seed
Siberian Wheatgrass (P27) 5.00
Russian Wildrye (Bozoisky) 5.00
Sandberg bluegrass 2.00
Wyoming big sagebrush 0.50
Total 12.50
- No seeding will occur from May 15 to September 15. Fall seeding is preferred and will be conducted after September 15 and prior to ground freezing [Shrub species will be seeded separately and will be seeded during the winter]. Spring seeding will be conducted after the frost leaves the ground and no later than May 15. (ACLLC)
- Weed-free mulch, silt fencing, waddles, hay bales, and other erosion control devices will be used on areas at risk of soil movement from wind and water erosion. (ACLLC)
- Mulch will be used if necessary to control erosion, create vegetation micro-sites, and retain soil moisture and may include hay, small-grain straw, wood fiber, live mulch, cotton, jute, or synthetic netting. Mulch will be free from mold, fungi, and will be certified free of noxious or invasive weed seeds. (ACLLC)
- If straw mulch is used, it will contain fibers long enough to facilitate
crimping and provide the greatest cover. (ACLLC)
- All site grading will balance cut and fill to the extent practicable to minimize potential effects from erosion. (BLM)
- Seeded areas will be fenced to exclude livestock until interim or final
reclamation is approved by the authorized officer. (ACLLC)
- The reserve pit shall be located in cut material, with at least 50% of the pit constructed below original ground level to prevent failure of the pit dike. Any fill dikes shall be compacted in lifts. (BLM)
|