Cement Bond Log
Exploration Technique: Cement Bond Log
Exploration Technique Information | |
---|---|
Exploration Group: | Downhole Techniques |
Exploration Sub Group: | Well Log Techniques |
Parent Exploration Technique: | Acoustic Logs |
Information Provided by Technique | |
Lithology: | |
Stratigraphic/Structural: | |
Hydrological: | |
Thermal: | |
Cost Information | |
Low-End Estimate (USD): | 0.85 85 centUSD / foot
8.5e-4 kUSD 8.5e-7 MUSD 8.5e-10 TUSD |
Median Estimate (USD): | 1.25 125 centUSD / foot
0.00125 kUSD 1.25e-6 MUSD 1.25e-9 TUSD |
High-End Estimate (USD): | 3.00 300 centUSD / foot
0.003 kUSD 3.0e-6 MUSD 3.0e-9 TUSD |
Time Required | |
Low-End Estimate: | 0.35 days 9.582478e-4 years / job
8.4 hours 0.05 weeks 0.0115 months |
Median Estimate: | 0.46 days 0.00126 years / job
11.04 hours 0.0657 weeks 0.0151 months |
High-End Estimate: | 0.69 days 0.00189 years / job
16.56 hours 0.0986 weeks 0.0227 months |
Additional Info | |
Cost/Time Dependency: | Depth, Temp, Resolution |