RAPID/BulkTransmission/Maine/Transmission
OpenEI/PageDescription Determine which state and federal permits apply to Siting and Regulation for Bulk Transmission projects in Maine.  +
OpenEI/PageKeyword RAPID Toolkit  + , Regulatory and Permitting Information Desktop  + , BulkTransmission  + , Maine  + , Transmission  +
Place Maine: Energy Resources +
PubUtilTxCert A person may need a Certificate of Public
A person may need a Certificate of Public Convenience and Necessity from the [[Maine Public Utilities Commission]] to construct transmission lines of 69 kV or more. [[Maine – 35-A ME. REV. STAT. §§ 3101-3195, Public Utilities - Electric Power – General Provisions|Me. Rev. Stat. Ann. tit. 35-A, § 3132-A]].
Me. Rev. Stat. Ann. tit. 35-A, § 3132-A]].  +
RegEntityDef A transmission and distribution utility is
A transmission and distribution utility is defined as “…a person, its lessees, trustees or receivers or trustees appointed by a court, owning, controlling, operating or managing a transmission and distribution plant for compensation within the State…” [[Maine – Me. Rev. Stat. Ann. tit. 35-A, §§ 2502 et seq., Definitions|Me. Rev. Stat. Ann. tit. 35-A, § 2502(1)(A)]].
Rev. Stat. Ann. tit. 35-A, § 2502(1)(A)]].  +
SitingAct [[Maine – 38 ME. REV. STAT. §§ 481-490 Site Location of Development Act]]  +
SitingAgency [[Maine Department of Environmental Protection]]  +
SitingAuth The [[Maine Public Utilities Commission]] has regulatory authority over transmission and distribution utilities lines.  +
SitingProcess Any person may need a Site Location of Development Permit.  +
SitingThreshold A Certificate of Public Convenience and Ne
A Certificate of Public Convenience and Necessity is required for transmission lines with a capacity of sixty-nine (69) kV or more. [[Maine – 35-A ME. REV. STAT. §§ 3101-3195, Public Utilities - Electric Power – General Provisions|Me. Rev. Stat. Ann. tit. 35-A, § 3132-A]].
Me. Rev. Stat. Ann. tit. 35-A, § 3132-A]].  +
SitingTimeframe There is no statutorily defined timeframe for approval.  +
Has query
"Has query" is a predefined property that represents meta information (in form of a subobject) about individual queries and is provided by Semantic MediaWiki.
RAPID/BulkTransmission/Maine/Transmission + , RAPID/BulkTransmission/Maine/Transmission + , RAPID/BulkTransmission/Maine/Transmission + , RAPID/BulkTransmission/Maine/Transmission + , RAPID/BulkTransmission/Maine/Transmission + , RAPID/BulkTransmission/Maine/Transmission + , RAPID/BulkTransmission/Maine/Transmission + , RAPID/BulkTransmission/Maine/Transmission + , RAPID/BulkTransmission/Maine/Transmission + , RAPID/BulkTransmission/Maine/Transmission + , RAPID/BulkTransmission/Maine/Transmission + , RAPID/BulkTransmission/Maine/Transmission +
Categories RAPID Topic , RAPID Toolkit , Bulk Transmission , Transmission
Modification date
"Modification date" is a predefined property that corresponds to the date of the last modification of a subject and is provided by Semantic MediaWiki.
21:45:06, 11 June 2018  +
Page has default form RAPID-Overview(Tech-Jurisdiction-Topic)  +