Browse wiki

From Open Energy Information

RAPID/BulkTransmission/Kansas/Transmission
OpenEI/PageDescription Determine which state and federal permits apply to Siting and Regulation for Bulk Transmission projects in Kansas.  +
OpenEI/PageKeyword RAPID Toolkit  + , Regulatory and Permitting Information Desktop  + , BulkTransmission  + , Kansas  + , Transmission  +
Place Kansas: Energy Resources +
PubUtilTxCert Electric utilities may need a Transmission
Electric utilities may need a Transmission Siting Permit from the [[Kansas Corporation Commission]] to “…prepare, or construct a electric transmission line, or exercise of the right of eminent domain…” for electric transmission line projects that are 230 kV or greater and at least 5 miles in length. [[Kansas - K.S.A. §§ 66-101 et seq., Public Utilities|K.S.A. §§ 66-1178]].
eq., Public Utilities|K.S.A. §§ 66-1178]].  +
RegEntityDef An "electric utility" means every public u
An "electric utility" means every public utility which owns, controls, operates, or manages any equipment, plant, or generating machinery for the production, transmission, delivery, or furnishing of electricity or electric power. [[Kansas - K.S.A. §§ 66-101 et seq., Public Utilities|K.S.A. §§ 66-1177(a)]]. A public utility includes "...all companies for the production, transmission, delivery or furnishing of heat, light, water or power." [[Kansas - K.S.A. §§ 66-101 et seq., Public Utilities|K.S.A. §§ 66-104(a)]].
., Public Utilities|K.S.A. §§ 66-104(a)]].  +
SitingAct [[Kansas - K.S.A. §§ 66-101 et seq., Public Utilities|K.S.A. §§ 66-1177, et seq., Kansas Siting Act]]  +
SitingAgency [[Kansas Corporation Commission]]  +
SitingAuth [[Kansas Corporation Commission]] has the authority to regulate electric transmission lines.  +
SitingProcess Kansas does not have a state comprehensive siting process for transmission project development.  +
SitingThreshold Electric transmission line projects that are 230 kV or greater and at least 5 miles in length.  +
SitingTimeframe [[Kansas Corporation Commission]] issues a final order regarding a Transmission Siting Permit within 120 days of the application filing date. [[Kansas - K.S.A. §§ 66-101 et seq., Public Utilities| K.S.A. §§ 66-1180]].  +
Has query
"Has query" is a predefined property that represents meta information (in form of a subobject) about individual queries and is provided by Semantic MediaWiki.
RAPID/BulkTransmission/Kansas/Transmission + , RAPID/BulkTransmission/Kansas/Transmission + , RAPID/BulkTransmission/Kansas/Transmission + , RAPID/BulkTransmission/Kansas/Transmission + , RAPID/BulkTransmission/Kansas/Transmission + , RAPID/BulkTransmission/Kansas/Transmission + , RAPID/BulkTransmission/Kansas/Transmission + , RAPID/BulkTransmission/Kansas/Transmission + , RAPID/BulkTransmission/Kansas/Transmission + , RAPID/BulkTransmission/Kansas/Transmission + , RAPID/BulkTransmission/Kansas/Transmission + , RAPID/BulkTransmission/Kansas/Transmission +
Categories RAPID Topic , RAPID Toolkit , Bulk Transmission , Transmission
Modification date
"Modification date" is a predefined property that corresponds to the date of the last modification of a subject and is provided by Semantic MediaWiki.
21:13:14, 11 June 2018  +
Page has default form RAPID-Overview(Tech-Jurisdiction-Topic)  +
hide properties that link here 
  No properties link to this page.
 
Enter the name of the page to start browsing from.