MHK Projects/Passamaquoddy Tribe Hydrokinetic Project
Coordinates 45.0233°, -67.0672°Latitude: 45.0234
Longitude: -67.0672
  +
FERC License Docket Number P-12710  +
Main Overseeing Organization UEK Corporation +
Number of Devices Deployed 15  +
Place Passamaquoddy Bay, ME + , Maine: Energy Resources + , United States: Energy Resources +
ProjectTechnology MHK Technologies/Underwater Electric Kite Turbines +
Project City Passamaquoddy Bay, ME +
Project Country United States: Energy Resources +
Project Details The Passamaquoddy Tribe received a grant f
The Passamaquoddy Tribe received a grant from the Bureau of Indian Affairs for $120,000 on May 27, 2008 to assist in funding the temporary positioning of the UEK 8 ft turbine at two locations. A contract with UEK and the Passamaquoddy Tribe was signed on September 5, 2008 to have UEK install a test underwater turbine on the FERC approved Passamaquoddy Tribe pre-proposal sites in Western Passage, Passamaquoddy Bay to help determine the feasibility of electrical power generation. UEK will conduct these tests from September 2008 through August 2009.
s from September 2008 through August 2009.  +
Project Installed Capacity (MW) 5  +
Project Phase Phase 1  +
Project Resource Current /Tidal  +
Project Start Date 1/1/2008  +
Project State/Province Maine: Energy Resources +
Categories Marine and Hydrokinetic Technology Projects
Modification date
"Modification date" is a predefined property that corresponds to the date of the last modification of a subject and is provided by Semantic MediaWiki.
22:39:13, 6 September 2013  +