NEPA Resource Analysis
|
Present, Potentially Affected +
|
NEPA Resource Comment
|
Ground disturbance would be kept to a minimum to help prevent soil erosion during construction. +
|
NEPA Resource Imposed Mitigation
|
Preserve vegetation where possible.
Comp … Preserve vegetation where possible.
Compact and seed topsoil on the perimeters of the drill pad and monofill and on the down-slope side of the access road.
Five culverts would be used to control stormwater flowing through the project area.
Silt fences would be installed to protect wetlands and drainages as described below:
*At the toe of the slope where the road crosses through any poorly drained areas
*At the north end of the drill pad to prevent sediment from contaminating the mapped wetland
to the north. Sediment would be removed and taken to the inert waste monofill when it has
reached 23 cm (9 inches) of accumulation
Minimize the amount of land disturbance and develop and implement stringent erosion and dust control practices. ingent erosion and dust control practices. +
|
NEPA Resources
|
Geothermal/Soils +
|