Missouri State Fish and Wildlife License Recommendations (12-MO-a)

Information current as of 2020
In Missouri, the Missouri Department of Conservation (MDC) may issue license recommendations to the Federal Energy Regulatory Commission (FERC) designed to protect, mitigate damage to, and enhance fish and wildlife resources for hydropower projects subject to FERC’s licensing requirements. 16 U.S.C. § 803(j).


The Federal Power Act (FPA) requires FERC to consult with state agencies responsible for the oversight and protection of fish, wildlife, and botanical resources. 18 C.F.R. §5.1(d); 18 C.F.R. § 4.38. The MDC is the state agency “charged with the control, management, conservation, and regulation of the bird, fish, game, forestry, and all wildlife resources of the state.” 3 C.S.R. § 30-1.010(1); Missouri – Mo. Rev. Stat. §§ 242.010 et seq., Missouri Wildlife and Forestry Law. If a project is subject to FERC licensing, section 10(j) of the FPA authorizes the MDC to issue recommendations to FERC to protect, mitigate damage to and enhance fish and wildlife resources. 16 U.S.C. § 803(j). FERC must consider the license recommendation(s) provided by the MDC and may require that the recommendation(s) become mandatory condition(s) of the FERC license. 16 U.S.C. § 803(j).

In addition to consulting with other federal, state, and tribal resource management agencies involved in the FERC licensing process, the MDC also reviews proposed hydropower projects at US Army Corps of Engineers (USACE) non-powered dams. The content on this page is limited in scope and was designed to consider hydropower development at USACE non-powered dams. Because USACE hydropower projects are not eligible for a FERC exemption, this page does not discuss FPA section 30(c), which authorizes state agencies to issue mandatory terms and conditions for hydropower projects which are exempt from FERC licensing requirements.



State Fish and Wildlife License Recommendations Process


12-MO-a.1 – Initiate Section 10(j) Analysis

For hydropower projects subject to FERC licensing, section 10(j) of the FPA authorizes MDC to issue recommendations to FERC in order to protect, mitigate damage to, and enhance those fish and wildlife species and their necessary habitat. 16 U.S.C. § 803(j).

MDC initiates the FPA section 10(j) analysis by reviewing the administrative record and identifying the potential impacts of the hydropower project on fish and wildlife species and their habitat.

12-MO-a.2 to 12-MO-a.3 – Are Additional Documents or Studies Needed?

If the record is incomplete, MDC may request that the developer provide additional documents. MDC may also conduct studies to address information gaps concerning baseline values or potential impacts of the proposed project.


12-MO-a.4 to 12-MO-a.5 – Section 10(j) Recommendations

Based upon MDC’s review of the hydropower project, MDC works with the developer to formulate FPA section 10(j) recommendations for the FERC license. 16 U.S.C. § 803(j). In developing its FPA section 10(j) recommendations, MDC considers and strives to maintain consistency with MDC policies and the requirements of the federal Endangered Species Act, and the management plan for the affected area. MDC’s recommendations may include measures addressing instream flow regimes, fish passage facilities, and/or vegetation and terrestrial wildlife management plans.

MDC submits its FPA section 10(j) recommendations to FERC. FERC must consider and accept any recommendation from MDC for the protection, mitigation, and enhancement of fish and wildlife affected by the project, unless FERC determines that:

  1. A recommendation is inconsistent with the purposes and requirements of the FPA or other applicable provisions of law; and
  2. The alternative conditions selected by FERC comply with the requirement to adequate protect, mitigate damages to, and enhance fish and wildlife. 16 U.S.C. § 803(j).

Once FERC issues a license, MDC continues to monitor the project to ensure the developer’s compliance with any conditions relevant to the projection, mitigation, and enhancement of fish and wildlife.