RAPID/BulkTransmission/Tennessee/Transmission

From Open Energy Information
RAPIDRegulatory and Permitting Information Desktop Toolkit
My Projects

Tennessee Bulk Transmission Transmission & Interconnection(8-TN)

In Tennessee, a developer should consult local zoning regulations during the transmission siting process. A developer may need a Certificate of Public Convenience and Necessity from the Tennessee Public Utility Commission for certain transmission projects. Although Tennessee does not have an interconnection process, a developer may need to follow the Tennessee Valley Authority (TVA) interconnection process for a project that connects to facilities owned and operated by the TVA.

More Information

Determine Which State and Federal Permits Apply

Use this overview flowchart and following steps to learn which federal and state permits apply to your projects.

Permitting at a Glance

Tennessee Federal

Transmission Siting Agency: Tennessee Public Utility Commission
Transmission Siting Process: A developer must obtain a Certificate of Public Convenience and Necessity (CCN) from the Tennessee Public Utility Commission (TPUC) to construct a generation or transmission facility. Tenn. Code Ann. §65-4-208(a). The TPUC regulates the construction of electric generating and transmission facilities primary pursuant to Tennessee – Tenn. Code Ann. §65-4-201 et seq., Certificate of Public Convenience and Necessity and Tennessee – Tenn. Comp. R. & Regs. 1220-1-1, Rules of the Tennessee Regulatory Authority Rules and Regulations of Practice and Procedure.
Regulated Entity Definition: A public utility is defined as an “individual, copartnership, association, corporation, or joint stock company…that own[s], operate[s], manage[s] or control[s], within the state, any…electric light…[,]…power, …or any other like system, plant or equipment, affected by and dedicated to the public use, under privileges, franchises, licenses, or agreements, granted by the state or by any political subdivision.” Tenn. Code Ann. §65-4-101(6)(a).
Permit Processing Timeframe: There is not defined time frame for approval.

Contact Information

No contacts have been added

| Add a Contact

List of Reference Sources