New Brunswick Bulk Transmission Siting & Regulation(8-NB)

In New Brunswick, a developer may need a Connection Approval from the New Brunswick – Transmission and System Operator Division to connect a new or modified facility to the Integrated Electricity System (IES) or for approval to make or modify a connection between the IES and a transmission system outside of New Brunswick. A developer may also need to enter into an Transmission System Agreement with the New Brunswick Power Corporation for the development of the New Brunswick transmission system.

More Information

Determine Which State and Federal Permits Apply

Use this overview flowchart and following steps to learn which federal and state permits apply to your projects.