Property:SitingTimeframe

From Open Energy Information

Property Name SitingTimeframe
Property Type Text
Description Used for RAPID Siting Permit Processing Timeframe

Pages using the property "SitingTimeframe"

Showing 25 pages using this property.

View (previous 25 | next 25) (20 | 50 | 100 | 250 | 500)

R
RAPID/BulkTransmission/Alaska/Transmission +There is no statutorily mandated timeframe for approval.  +
RAPID/BulkTransmission/Arizona/Transmission +Certificate of Environmental Compatibility: 240 days  +
RAPID/BulkTransmission/Arkansas/Transmission +There is no statutorily mandated timeframe for approval.  +
RAPID/BulkTransmission/California/Transmission +There is no statutorily mandated timeframe for approval.  +
RAPID/BulkTransmission/Colorado/Transmission +60 days  +
RAPID/BulkTransmission/Connecticut/Transmission +There is no statutorily mandated timeframe for approval.  +
RAPID/BulkTransmission/Delaware/Transmission +There is no statutorily defined timeframe.  +
RAPID/BulkTransmission/Florida/Transmission +40 days. [[Florida – Fla. Stat. §§ 403.52 et seq., Florida Electric Transmission Line Siting Act|Fla. Stat. § 403.529]]  +
RAPID/BulkTransmission/Georgia/Transmission +There is no statutorily defined processing timeframe.  +
RAPID/BulkTransmission/Hawaii/Transmission +There is no statutorily defined time frame for approval.  +
RAPID/BulkTransmission/Idaho/Transmission +There is no statutorily defined timeframe.  +
RAPID/BulkTransmission/Illinois/Transmission +There is no statutorily defined timeframe for approval, except for projects that go through the expedited review process. The expedited review process must be complete within 150 days after the application is filed. [[Illinois Public Utilities Act (220 I.L.C.S §§ 5 et seq.)| 220 I.L.C.S § 5/8-406.1(g)]].  +
RAPID/BulkTransmission/Indiana/Transmission +There is no statutorily mandated timeframe for approval.  +
RAPID/BulkTransmission/Iowa/Transmission +There is no statutorily defined timeframe for approval.  +
RAPID/BulkTransmission/Kansas/Transmission +[[Kansas Corporation Commission]] issues a final order regarding a Transmission Siting Permit within 120 days of the application filing date. [[Kansas - K.S.A. §§ 66-101 et seq., Public Utilities| K.S.A. §§ 66-1180]].  +
RAPID/BulkTransmission/Kentucky/Transmission +90 days  +
RAPID/BulkTransmission/Louisiana/Transmission +There is no statutorily mandated timeframe for approval.  +
RAPID/BulkTransmission/Maine/Transmission +There is no statutorily defined timeframe for approval.  +
RAPID/BulkTransmission/Maryland/Transmission +1 year  +
RAPID/BulkTransmission/Massachusetts/Transmission +There is no statutorily defined timeframe for approval.  +
RAPID/BulkTransmission/Michigan/Transmission +There is no statutorily defined timeframe for approval.  +
RAPID/BulkTransmission/Minnesota/Transmission +12 months  +
RAPID/BulkTransmission/Mississippi/Transmission +There is no statutorily defined timeframe for approval.  +
RAPID/BulkTransmission/Missouri/Transmission +There is no statutorily defined timeframe for approval.  +
RAPID/BulkTransmission/Montana/Transmission +9 months  +, as little as 90 days for expedited review. [[Montana – Mont. Code Ann. §§ 75-20-201 et seq., Certification Proceedings|Mont. Code Ann. §75-20-216]]  +, [[Montana – Mont. Code Ann. §§ 75-20-201 et seq., Certification Proceedings|Mont. Code Ann. §75-20-231]].  +