Property:SitingThreshold

From Open Energy Information

Property Name SitingThreshold
Property Type Text
Description Used by the RAPID toolkit state level permitting forms.

Pages using the property "SitingThreshold"

Showing 25 pages using this property.

View (previous 25 | next 25) (20 | 50 | 100 | 250 | 500)

R
RAPID/BulkTransmission/Arizona/Transmission +To construct transmission lines with a voltage of 115kV or greater. [[ARS 40 - Public Utilities and Carriers | ARS 40-360(10) and 40-360.03]].  +
RAPID/BulkTransmission/Connecticut/Transmission +To construct a transmission facility of 69 kV or more. [[Connecticut – Conn. Gen. Stat. §§ 16-50 et seq., Public Utility Environmental Standards Act|C.G.S. §16-50k(a)]].  +
RAPID/BulkTransmission/Delaware/Transmission +Delaware does not require other approvals from the public utility commission for transmission projects.  +
RAPID/BulkTransmission/Florida/Transmission +To construct an electric transmission line of 230 kV or greater  +
RAPID/BulkTransmission/Georgia/Transmission +A line that is at least 115 kV or more with a length of at least one mile.  +
RAPID/BulkTransmission/Iowa/Transmission +69 kV or greater [[Iowa – Iowa Code §§ 478 et seq., Electric Transmission Lines | I.C. § 478.1(3)]].  +
RAPID/BulkTransmission/Kansas/Transmission +Electric transmission line projects that are 230 kV or greater and at least 5 miles in length.  +
RAPID/BulkTransmission/Kentucky/Transmission +A non-regulated electric transmission line is an electric transmission line of 69 kV or more and related appurtenances for which no Certificate of Public Convenience and Necessity is required, which is not operated as an activity regulated by the [[Kentucky Public Service Commission]].  +
RAPID/BulkTransmission/Maine/Transmission +A Certificate of Public Convenience and Necessity is required for transmission lines with a capacity of sixty-nine (69) kV or more. [[Maine – 35-A ME. REV. STAT. §§ 3101-3195, Public Utilities - Electric Power – General Provisions|Me. Rev. Stat. Ann. tit. 35-A, § 3132-A]].  +
RAPID/BulkTransmission/Massachusetts/Transmission +A new electric transmission line of 69 kV or more and one mile or more in length on a new transmission corridor  +, or a new electric transmission line 115 kV or more which is 10 miles or more in length on an existing transmission corridor  +, or an ancillary structure which is an integral part of the operation of any transmission line. [[Massachusetts - Mass. Gen. Laws ch. 164 et seq., Manufacture and Sale of Gas and Electricity|M.G.L. 164 § 69G]].  +
RAPID/BulkTransmission/Minnesota/Transmission +100 kV or more and greater than 1,500 feet in length  +
RAPID/BulkTransmission/Mississippi/Transmission +Mississippi does not have a comprehensive siting process.  +
RAPID/BulkTransmission/Missouri/Transmission +Missouri does not have a comprehensive siting process.  +
RAPID/BulkTransmission/Montana/Transmission +To construct a facility, which includes electric transmission lines and associated facilities of 69 kV or more.  +
RAPID/BulkTransmission/Nebraska/Transmission +Any electric generating facility, or transmission line, or related facilities constructed or acquired by any electric supplier “carrying more than seven (700) volts” must first receive [[Nebraska Power Review Board]] approval. [[Nebraska – 70 N.R.S. §§ 101 et seq., Power Districts and Corporations | 70 N.R.S. § 1012(1)]]  +, [[Nebraska Regulations – 285 N.A.C. §§ 2-001 et seq., Rules and Procedures for Construction of Electric Transmission Lines | 285 N.A.C. § 2-002]].  +
RAPID/BulkTransmission/New Hampshire/Transmission +To construct, operate, or maintain any energy facility. [[New Hampshire – N.H. REV. STAT. ANN. §§ 162-H et seq., Energy Facility Evaluation, Siting, Construction, and Operation Act|RSA §16-H:2]]. [[New Hampshire – N.H. REV. STAT. ANN. §§ 162-H et seq., Energy Facility Evaluation, Siting, Construction, and Operation Act|RSA §16-H:5(I)]].  +
RAPID/BulkTransmission/New Jersey/Transmission +The construction of an electric transmission line through more than one municipality.  +
RAPID/BulkTransmission/New Mexico/Transmission +230 kV or more  +
RAPID/BulkTransmission/North Dakota/Transmission +To construct or operate electric transmission lines that exceed 115 kV and extends at least one more or more. [[North Dakota – N.D. Century Code §§ 49-22 et seq., Energy Conversion and Transmission Facility Siting Act|N.D. Century Code § 49-22-07]]  +, [[North Dakota – N.D. Century Code §§ 49-22 et seq., Energy Conversion and Transmission Facility Siting Act|N.D. Century Code § 49-22-08.1]].  +
RAPID/BulkTransmission/Ohio/Transmission +To construct a major utility facility of 100 kV or more.  +
RAPID/BulkTransmission/Oregon/Transmission +To construct an energy facility of 230 kV or for a line greater than 10 miles in length. [[Oregon ORS 469, Energy Facilities | O.R.S. 469.320]].  +
RAPID/BulkTransmission/Pennsylvania/Transmission +To construct a high-voltage transmission lines or 100 kV or more. [[Pennsylvania - 52 PA. Code. §57.71 et seq., Commission Review of Siting and Construction of Electric Transmission Lines (1978)|52 PA. Code. §57.71(1978)]].  +
RAPID/BulkTransmission/Rhode Island/Transmission +To construct or alter a major energy facility, which includes transmission lines with a capacity of 69 kV or greater. [[Rhode Island – tit. 42 R.I. Gen. Laws §§ 98 et seq., Energy Facility Siting Act|R.I. Stat. Ann. §42-98-4]].  +
RAPID/BulkTransmission/South Dakota/Transmission +To construct a transmission facility which includes electric transmission lines and associated facilities with a design of more than 115 kV. [[South Dakota—South Dakota Stat. Ann. §§49-41B-1 et seq., Energy Conversion and Transmission Facilities|S.D. Stat. Ann. §49-41B-2.1]].  +
RAPID/BulkTransmission/Utah/Transmission +To construct or operate of a high voltage transmission line of 230 kV or more, or an upgraded high voltage transmission line. [[Utah—Utah Code. Ann. §§54-1-1 et seq., Public Service Commission|UT. Code. Ann. §§54-18-102 – 54-18-201]].  +