Property Type Text
Description Used by the RAPID toolkit state level permitting forms.

Pages using the property "EnvReview"

Showing 25 pages using this property.

View (previous 25 | next 25) (20 | 50 | 100 | 250 | 500)

R
RAPID/BulkTransmission/Alaska/Environment +Developers must participate in a best interests finding for certain projects. The best interests finding is a written analysis that describes for the public the facts and applicable law that are relevant to the disposal and gives a decision based on certain factors.  +
RAPID/BulkTransmission/Arizona/Environment +To obtain a Certificate of Environmental Compatibility the applicant must provide a description of the proposed facility and any environmental studies the applicant has or intends to perform in connection with the proposed facility. The [[Arizona Transmission Line Siting Committee]] considers existing state and local plans, wildlife, noise pollution, and existing environmentally significant sites. [[Ariz. Admin. Code § R14-3-219]]; [[A.R.S. § 40-360.06]].  +
RAPID/BulkTransmission/California/Environment +Proposed transmission project of 200 kV or higher, that require a Certificate of Public Convenience and Necessity and those proposed projects of 50 kV to 200 kV, that require a Permit to Construct must comply with the California Environmental Quality Act.  +
RAPID/BulkTransmission/Colorado/Environment +Colorado does not have a state specific environmental review process.  +
RAPID/BulkTransmission/Connecticut/Environment +Connecticut does not have a state specific environmental review process.  +
RAPID/BulkTransmission/Federal/Environment +[[National Environmental Policy Act]]  +
RAPID/BulkTransmission/Hawaii/Environment +Hawaii's State Environmental Policy Act requires a environmental asssessment, unless exempt, of most proposed projects, and if the impact of the proposed project is significant the project must undergo the environmental impact statement process.  +
RAPID/BulkTransmission/Idaho/Environment +Idaho does not have a state specific environmental review process.  +
RAPID/BulkTransmission/Illinois/Environment +Illinois does not have a state specific environmental review process.  +
RAPID/BulkTransmission/Indiana/Environment +Indiana has a state specific environmental review process, but the review does not apply when state agencies are issuing permits or licenses.  +
RAPID/BulkTransmission/Iowa/Environment +Iowa does have a state specific environmental review process.  +
RAPID/BulkTransmission/Kansas/Environment +Kansas does not have a state specific environmental review process.  +
RAPID/BulkTransmission/Maine/Environment +Maine does not have a state specific environmental review process.  +
RAPID/BulkTransmission/Massachusetts/Environment +Bulk transmission projects must comply with the Massachusetts Environmental Policy Act (MEPA). Depending on the size and scope of a proposed project, a developer of a project that requires a permit from a state agency may have to submit environmental reports that have varying levels of detail in compliance with MEPA. [[Massachusetts – 301 CODE MASS. REGS. §§ 11.00 et seq., Massachusetts Environmental Policy Act Regulations|301 C.M.R. § 11.05(1)]]; [[Massachusetts – MASS. GEN. LAWS ch. 30 §§ 61 et seq., Massachusetts Environmental Policy Act|M.G.L. c. 30 § 62A]].  +
RAPID/BulkTransmission/Michigan/Environment +Michigan does have a state specific environmental review process.  +
RAPID/BulkTransmission/Minnesota/Environment +Bulk transmission projects must comply with the [[Minnesota – Minn. Stat. §§ 116D et seq., Environmental Policy|Minnesota Environmental Policy Act]]. The scope of the environmental review depends on the size of the project and the lead agency in charge. Depending on the type of project the lead agency may issue either an Environmental Report, Environmental Assessment, or an Environmental Impact Statement to assist in the decision to issue a Certificate of Need or Route Permit. [[Minnesota Department of Commerce]]; [[Minnesota Public Utilities Commission]], the local governmental unit.  +
RAPID/BulkTransmission/Missouri/Environment +Missouri does not have a state specific environmental review process.  +
RAPID/BulkTransmission/Montana/Environment +If a project requires a state agency action, the agency and the developer must comply with the [[M.C.A. 75-1-101 - Montana Environmental Policy Act | Montana Environmental Policy Act]] (MEPA) unless the activities are otherwise exempt/excluded under MEPA.  +
RAPID/BulkTransmission/Nebraska/Environment +Nebraska does not have a state specific environmental review process.  +
RAPID/BulkTransmission/Nevada/Environment +Utility facilities must go through a Utility Environmental Protection Act review prior to commencing construction.  +
RAPID/BulkTransmission/New Hampshire/Environment +New Hampshire does not have a state specific environmental review process.  +
RAPID/BulkTransmission/New Mexico/Environment +New Mexico does not have a state specific environmental review process.  +
RAPID/BulkTransmission/New York/Environment +Major utility transmission facilities that require a Certificate of Environmental Compatibility and Public Need (CECPN) from the [[New York State Public Service Commission]] are not subject to New York’s [[New York - State Environmental Quality Review Act|State Environmental Quality Review Act]] (SEQR). Transmission lines that do not qualify as a major utility transmission facility may be subject to SEQR if they require discretionary approvals from any state agency. [[New York Division of Environmental Conservation – SEQR Handbook|New York Department of Environmental Conservation – SEQR Handbook at 35]].  +
RAPID/BulkTransmission/North Dakota/Environment +North Dakota does not have a state specific environmental review process.  +
RAPID/BulkTransmission/Ohio/Environment +Ohio does not have a state specific environmental review process.  +