Interagency Task Force on Improving Hydroelectric Licensing Processes – Guidelines to Consider for Participating in the Alternative Licensing Process

From Open Energy Information


OpenEI Reference LibraryAdd to library

Permitting/Regulatory Guidance - Guide/Handbook: Interagency Task Force on Improving Hydroelectric Licensing Processes – Guidelines to Consider for Participating in the Alternative Licensing Process

Abstract
The Guidelines to Consider for Participating in the Alternative Licensing Process were developed by the Interagency Task Force to help participants in the process. The Interagency Task Force consists of representatives from FERC, the Council on Environmental Quality, Department of Commerce, Department of the Interior, Department of Agriculture, and the Environmental Protection Agency.

Author 
Interagency Task Force on Improving Hydroelectric Licensing Processes






Published 
Interagency Task Force on Improving Hydroelectric Licensing Processes, 2000



DOI 
Not Provided
Check for DOI availability: http://crossref.org


Online 
Internet link for Interagency Task Force on Improving Hydroelectric Licensing Processes – Guidelines to Consider for Participating in the Alternative Licensing Process
Citation

Interagency Task Force on Improving Hydroelectric Licensing Processes. 2000. Interagency Task Force on Improving Hydroelectric Licensing Processes – Guidelines to Consider for Participating in the Alternative Licensing Process. Interagency Task Force on Improving Hydroelectric Licensing Processes. Guidelines to Consider for Participating in the Alternative Licensing Process. 39p. Guide/Handbook sent to (!)