Line 3: Line 3:
 
|Flowchart=File:3-AZ-b - State Land Right-of-Way.pdf
 
|Flowchart=File:3-AZ-b - State Land Right-of-Way.pdf
 
|Technology=Bulk Transmission
 
|Technology=Bulk Transmission
|PermitOverview=Developers who plan to construct transmission lines across Arizona state land must obtain a Right-of-Way (ROW) from the Arizona State Land Department (ASLD).  The ASLD is responsible for administering all laws relating to lands owned by, belonging to and under the control of the state. See [[A.R.S. § 37-102: State Land Department - Powers and Duties | A.R.S. 37-102]]. [[A.R.S. § 37-461: Grants of Rights-of-Way and Site for Public Uses | A.R.S. 37-461]] provides the ASLD with the authority to grant ROWs, for any purpose it deems necessary, on and over state lands. ROWs may be subject to terms and conditions, as required by the ASDL.  Transmission lines are generally permitted for a term of 50 years. See the [[Arizona Right-of-Way Instruction Sheet | Right-of-Way Instruction Sheet]].  Regulations governing ROWs over Arizona state land can be found at [[A.A.C. R12-5-801: Rights-of-Way | A.A.C. R12-5-801]].
+
|InformationCurrentYear=2020
|Description===3-AZ-b.1 to 3-AZ-b.2 – Contact the Arizona State Land Department; Hold Pre-Application Conference==
+
|PermitOverview=In Arizona, a developer may need a Right-of-Way from the [[Arizona State Land Department]] (ASLD) for transmission lines across lands owned by, belonging to and under the control of the state. [[A.R.S. § 37-102: State Land Department - Powers and Duties | Ariz. Rev. Stat. § 37-102]]. ASLD has the authority to grant ROWs, for any purpose it deems necessary, on and over state lands [[A.R.S. § 37-461: Grants of Rights-of-Way and Site for Public Uses | Ariz. Rev. Stat. § 37-461]]. ROWs may be subject to terms and conditions, as required by the ASLD.  Transmission lines are generally permitted for a term of 50 years. [[Arizona Right-of-Way Instruction Sheet | Right-of-Way Instruction Sheet]].   
 +
 
 +
 
 +
ASLD regulates rights-of-way pursuant to [[A.R.S. § 37-102: State Land Department - Powers and Duties |Ariz .Rev. Stat. §§ 37-101–37-133]], [[A.R.S. § 37-461: Grants of Rights-of-Way and Site for Public Uses |Ariz. Rev. Stat. §§ 37-201–37-620.31]], and [[A.A.C. R12-5-801: Rights-of-Way |Ariz. Admin. Code §§ R12-5-801–R12-5-803]]
 +
|Description===3-AZ-b.1 to 3-AZ-b.2 – Contact the Arizona State Land Department==
  
 
Although the ROW process is technically initiated by the submission of an application, the developer may contact ASLD’s real estate division in order to discuss specific properties or to schedule a preliminary application conference.  Because ROW applications are not posted online, they must be obtained directly from the ASLD.  The Developer may pick up an application in person at the ASLD or contact the Rights-of-Way division and request that a copy be mailed.  See [[Arizona State Land Department Rights-of-Way Website]].
 
Although the ROW process is technically initiated by the submission of an application, the developer may contact ASLD’s real estate division in order to discuss specific properties or to schedule a preliminary application conference.  Because ROW applications are not posted online, they must be obtained directly from the ASLD.  The Developer may pick up an application in person at the ASLD or contact the Rights-of-Way division and request that a copy be mailed.  See [[Arizona State Land Department Rights-of-Way Website]].
Line 10: Line 14:
 
==3-AZ-b.3 to 3-AZ-b.5 – Right-of-Way Application==
 
==3-AZ-b.3 to 3-AZ-b.5 – Right-of-Way Application==
  
As stated above, the ROW application process is technically initiated when the developer submits an ROW application to the ASLD.  Entities that may apply for a ROW are listed in [[A.A.C. R12-5-801: Rights-of-Way | A.A.C. R12-5-801(C)(1)(a)]].  A separate application must be submitted for each county crossed.  See [[A.A.C. R12-5-801: Rights-of-Way | A.A.C. R12-5-801(C)(2)]].  The following information must be included in the application:
+
As stated above, the ROW application process is technically initiated when the developer submits a ROW application to the ASLD.  Entities that may apply for a ROW are listed in [[A.A.C. R12-5-801: Rights-of-Way | Ariz. Admin. Code § R12-5-801(C)(1)(a)]].  A separate application must be submitted for each county crossed.  See [[A.A.C. R12-5-801: Rights-of-Way | Ariz. Admin. Code § R12-5-801(C)(2)]].  The following information must be included in the application:
 
*Name and address of the developer;
 
*Name and address of the developer;
 
*Statement whether developer is an individual, partnership or corporation, or governmental agency of the state or political subdivision and municipal corporation thereof;
 
*Statement whether developer is an individual, partnership or corporation, or governmental agency of the state or political subdivision and municipal corporation thereof;
Line 24: Line 28:
 
*The nature of the right-of-way (the right-of-way is temporary or permanent; the right-of-way requires exclusive use or to what extent; a right- of-way through a given area);
 
*The nature of the right-of-way (the right-of-way is temporary or permanent; the right-of-way requires exclusive use or to what extent; a right- of-way through a given area);
 
*A survey of the land for which application is being made showing distance and direction from a known cadastral survey point in each section;
 
*A survey of the land for which application is being made showing distance and direction from a known cadastral survey point in each section;
*Location of improvements or crops on land under application over which proposed routes of right-of-way will pass (information required in [[A.A.C. R12-5-801: Rights-of-Way | A.A.C. R12-5-801(C)(3)(a)(ix)]] and [[A.A.C. R12-5-801: Rights-of-Way | A.A.C. R12-5-801(C)(3)(a)(x)]] must be conveyed by means of accurate plat or drawing accompanying the application form);
+
*Location of improvements or crops on land under application over which proposed routes of right-of-way will pass (information required in [[A.A.C. R12-5-801: Rights-of-Way | Ariz. Admin. Code § R12-5-801(C)(3)(a)(ix)]] and [[A.A.C. R12-5-801: Rights-of-Way | Ariz. Admin. Code § R12-5-801(C)(3)(a)(x)]] must be conveyed by means of accurate plat or drawing accompanying the application form);
 
*Evidence from surface lessee and all other right holders in the land applied for giving consent to the new right-of-way or objection thereto.
 
*Evidence from surface lessee and all other right holders in the land applied for giving consent to the new right-of-way or objection thereto.
  
See [[A.A.C. R12-5-801: Rights-of-Way | A.A.C. R12-5-801(C)(3)(a)]].
+
See [[A.A.C. R12-5-801: Rights-of-Way | Ariz. Admin. Code § R12-5-801(C)(3)(a)]].
The application should also include information about what the developer proposes to construct and the purpose of the ROW.  See the [[Arizona Right-of-Way Instruction Sheet | Right-of-Way Instruction Sheet]].  Supplemental forms may be required for specific types of ROW applications.  For example, utilities must submit [[Form RW-U: Utilities | Form RW-U]] along with the ROW application.  See [[Arizona State Land Department Applications and Permits Website]].  In addition, the ASLD may require the developer to submit additional information if necessary.  See [[A.A.C. R12-5-801: Rights-of-Way | A.A.C. R12-5-801(C)(3)(b)]].  The application must be accompanied by the appropriate filing fee, signed, and returned to the ASLD.  Each application is reviewed by ASDL for completeness.  See [[A.A.C. R12-5-801: Rights-of-Way | A.A.C. R12-5-801(C)(5)(a)-(b)]].
+
The application should also include information about what the developer proposes to construct and the purpose of the ROW.  See the [[Arizona Right-of-Way Instruction Sheet | Right-of-Way Instruction Sheet]].  Supplemental forms may be required for specific types of ROW applications.  For example, utilities must submit [[Form RW-U: Utilities | Form RW-U]] along with the ROW application.  See [[Arizona State Land Department Applications and Permits Website]].  In addition, the ASLD may require the developer to submit additional information if necessary.  See [[A.A.C. R12-5-801: Rights-of-Way | Ariz. Admin. Code § R12-5-801(C)(3)(b)]].  The application must be accompanied by the appropriate filing fee, signed, and returned to the ASLD.  Each application is reviewed by ASLD for completeness.  See [[A.A.C. R12-5-801: Rights-of-Way | Ariz. Admin. Code § R12-5-801(C)(5)(a)-(b)]].
  
==3-AZ-b.6 to 3-AZ-b.9 – Process Application; Does the ASLD Approve the Right-of-Way?; Conduct Appraisal; Perform Required Surveys==
+
==3-AZ-b.6 to 3-AZ-b.9 – Process Application ==
  
 
More complex ROW applications may take longer to process.  Processing times vary from 12 to 16 months.  See [[Arizona State Land Department Rights-of-Way Website]].  The ASLD conducts a preliminary review of the application to “evaluate impact and suitability as to the acceptability of the proposed alignment.”  In some cases, a field inspection may be required.  The developer will be notified if the alignment is acceptable.  In some circumstances, additional surveys may be required.  See the [[Arizona Right-of-Way Instruction Sheet | Right-of-Way Instruction Sheet]].   
 
More complex ROW applications may take longer to process.  Processing times vary from 12 to 16 months.  See [[Arizona State Land Department Rights-of-Way Website]].  The ASLD conducts a preliminary review of the application to “evaluate impact and suitability as to the acceptability of the proposed alignment.”  In some cases, a field inspection may be required.  The developer will be notified if the alignment is acceptable.  In some circumstances, additional surveys may be required.  See the [[Arizona Right-of-Way Instruction Sheet | Right-of-Way Instruction Sheet]].   
If the ASLD decides to approve the ROW, it will determine the rental fees after conducting an appraisal.  See [[A.A.C. R12-5-801: Rights-of-Way | A.A.C. R12-5-801(C)(5)(c)]].  The appraisal is based on the fair market value of the land.  See the  [[Arizona Right-of-Way Instruction Sheet | Right-of-Way Instruction Sheet]].   
+
If the ASLD decides to approve the ROW, it will determine the rental fees after conducting an appraisal.  See [[A.A.C. R12-5-801: Rights-of-Way | Ariz. Admin. Code § R12-5-801(C)(5)(c)]].  The appraisal is based on the fair market value of the land.  See the  [[Arizona Right-of-Way Instruction Sheet | Right-of-Way Instruction Sheet]].   
  
 
==3-AZ-b.10 – Does ASLD Approve the Right-of-Way?==
 
==3-AZ-b.10 – Does ASLD Approve the Right-of-Way?==
Line 40: Line 44:
 
==3-AZ-b.11 to 3-AZ-b.12 – Right-of-Way Contract==
 
==3-AZ-b.11 to 3-AZ-b.12 – Right-of-Way Contract==
  
If the ASLD approves the ROW, it will draft a ROW contract that contains necessary terms and conditions.  See [[A.R.S. § 37-461: Grants of Rights-of-Way and Site for Public Uses | A.R.S. 37-461]].  It must also provide for the following:
+
If the ASLD approves the ROW, it will draft a ROW contract that contains necessary terms and conditions.  See [[A.R.S. § 37-461: Grants of Rights-of-Way and Site for Public Uses | Ariz. Rev. Stat. § 37-461]].  It must also provide for the following:
*Payment to the [ASLD] of the amount established by the [ASDL] after determination of the true appraised value.
+
*Payment to the [ASLD] of the amount established by the [ASLD] after determination of the true appraised value.
 
*The installation and construction of necessary machinery, equipment and facilities with the right of removal within 90 days after expiration or termination of the right-of-way.
 
*The installation and construction of necessary machinery, equipment and facilities with the right of removal within 90 days after expiration or termination of the right-of-way.
*Fencing and other protective requirements deemed necessary by the [ASDL].
+
*Fencing and other protective requirements deemed necessary by the [ASLD].
*That the grantee (developer) must restore the surface of the land within the right-of-way to a reasonable condition as required by the [ASDL].
+
*That the grantee (developer) must restore the surface of the land within the right-of-way to a reasonable condition as required by the [ASLD].
 
*That the grantee (developer) will indemnify, hold and save grantor harmless against all loss, damage, liability, expenses, costs and charges incident to or resulting in any way from the use, condition or occupation of the land.
 
*That the grantee (developer) will indemnify, hold and save grantor harmless against all loss, damage, liability, expenses, costs and charges incident to or resulting in any way from the use, condition or occupation of the land.
 
*A statement of the purpose for which the right- of-way was granted.
 
*A statement of the purpose for which the right- of-way was granted.
*The right of the grantee (developer) to assign the right-of- way, provided that such an assignment can not become effective until approved in writing by the [ASDL] as being in the best interests of the state and until a copy thereof is filed with the [ASDL].
+
*The right of the grantee (developer) to assign the right-of- way, provided that such an assignment can not become effective until approved in writing by the [ASLD] as being in the best interests of the state and until a copy thereof is filed with the [ASLD].
*The right of termination of the right-of-way by the grantee (developer) at any time during its term by giving the [ASDL]  30 days notice of termination in writing, provided that the grantee (developer) is not delinquent in any payments and has complied with all conditions on the date of termination.
+
*The right of termination of the right-of-way by the grantee (developer) at any time during its term by giving the [ASLD]  30-days notice of termination in writing, provided that the grantee (developer) is not delinquent in any payments and has complied with all conditions on the date of termination.
  
See [[A.A.C. R12-5-801: Rights-of-Way | A.A.C. R12-5-801(D)(4)]].   
+
See [[A.A.C. R12-5-801: Rights-of-Way | Ariz. Admin. Code § R12-5-801(D)(4)]].   
  
The ASDL may also require the developer to post a bond to guarantee payment under the contract, guarantee restoration of the land after the ROW has expired, or cover loss associated with damage or destruction resulting from the construction or use of the ROW.  See [[A.A.C. R12-5-801: Rights-of-Way | A.A.C. R12-5-801(D)(7)]].   
+
The ASLD may also require the developer to post a bond to guarantee payment under the contract, guarantee restoration of the land after the ROW has expired, or cover loss associated with damage or destruction resulting from the construction or use of the ROW.  See [[A.A.C. R12-5-801: Rights-of-Way | Ariz. Admin. Code § R12-5-801(D)(7)]].   
The ASLD issues the ROW contract once the developer has demonstrated compliance with all of the application requirements.  The developer has 60 days from the date of mailing to execute and return the ROW contract with all applicable fees and rents.  Failure to do so may result in the cancellation of the ROW.  See [[A.A.C. R12-5-801: Rights-of-Way | A.A.C. R12-5-801(C)(8)]].
+
The ASLD issues the ROW contract once the developer has demonstrated compliance with all of the application requirements.  The developer has 60 days from the date of mailing to execute and return the ROW contract with all applicable fees and rents.  Failure to do so may result in the cancellation of the ROW.  See [[A.A.C. R12-5-801: Rights-of-Way | Ariz. Admin. Code § R12-5-801(C)(8)]].
  
 
==3-AZ-b.13 – Does the Developer Appeal the Decision?==
 
==3-AZ-b.13 – Does the Developer Appeal the Decision?==
Line 59: Line 63:
  
 
==3-AZ-b.14 – Notice of Appeal==
 
==3-AZ-b.14 – Notice of Appeal==
The developer must file a written Notice of Appeal to ASLD containing a clear and concise statement of the grounds for appeal and the specific relief sought. [[A.A.C. R12-5-2301 through 2315 Board of Appeals | R12-5-2302]]
+
The developer must file a written Notice of Appeal to ASLD containing a clear and concise statement of the grounds for appeal and the specific relief sought. [[A.A.C. R12-5-2301 through 2315 Board of Appeals | Ariz. Admin. Code § R12-5-2302]]
  
 
==3-AZ-b.15 – Set a Date for the Hearing==
 
==3-AZ-b.15 – Set a Date for the Hearing==
The County Clerk must set a date for the hearing within 10 days of receipt of the Notice of Appeal. [[A.A.C. R12-5-2301 through 2315 Board of Appeals | R12-5-2303(A)]].  
+
The County Clerk must set a date for the hearing within 10 days of receipt of the Notice of Appeal. [[A.A.C. R12-5-2301 through 2315 Board of Appeals | Ariz. Admin. Code § R12-5-2303(A)]].  
  
 
==3-AZ-b.16 – Provide Notice of Hearing==
 
==3-AZ-b.16 – Provide Notice of Hearing==
The County Clerk must serve notice of the hearing, by certified mail or personal service, to the developer at least 30 days before the hearing. [[A.A.C. R12-5-2301 through 2315 Board of Appeals | R12-5-2303]]. The Notice of Hearing must contain a statement:
+
The County Clerk must serve notice of the hearing, by certified mail or personal service, to the developer at least 30 days before the hearing. [[A.A.C. R12-5-2301 through 2315 Board of Appeals | Ariz. Admin. Code § R12-5-2303(B)]]. The Notice of Hearing must contain a statement:
 
*Identifying the parties and matters asserted;
 
*Identifying the parties and matters asserted;
 
*Establishing the date, time, and place of the hearing;
 
*Establishing the date, time, and place of the hearing;
 
*Identifying the legal authority and jurisdiction under which the hearing is to be held;
 
*Identifying the legal authority and jurisdiction under which the hearing is to be held;
*Advising the parties of the requirements of [[A.A.C. R12-5-2301 through 2315 Board of Appeals | R12-5-2305]];
+
*Advising the parties of the requirements of [[A.A.C. R12-5-2301 through 2315 Board of Appeals | Ariz. Admin. Code § R12-5-2305]];
*Referencing the particular statutes and rules involved. [[A.A.C. R12-5-2301 through 2315 Board of Appeals | R12-5-2303]].  
+
*Referencing the particular statutes and rules involved. [[A.A.C. R12-5-2301 through 2315 Board of Appeals | Ariz. Admin. Code § R12-5-2303(B)]].  
  
 
==3-AZ-b.17 – Conduct Hearing on Decision==
 
==3-AZ-b.17 – Conduct Hearing on Decision==
The Arizona State Land Department's Board of Appeals (the “Board”) will conduct a hearing to review the decision to deny a right-of-way.  
+
The Arizona State Land Department's Board of Appeals (Board) will conduct a hearing to review the decision to deny a right-of-way.  
  
 
==3-AZ-b.18 to 3-AZ-b.19 – Does the Board Approve the Right-of-Way?==
 
==3-AZ-b.18 to 3-AZ-b.19 – Does the Board Approve the Right-of-Way?==
The Board must render a final decision within 60 days after the hearing. [[A.A.C. R12-5-2301 through 2315 Board of Appeals | R12-5-2314(A)]]. The Board must include the findings of fact and conclusions of law that led them to their final decision. [[A.A.C. R12-5-2301 through 2315 Board of Appeals | R12-5-2314(B)]].  
+
The Board must render a final decision within 60 days after the hearing. [[A.A.C. R12-5-2301 through 2315 Board of Appeals | Ariz. Admin. Code § R12-5-2314(A)]]. The Board must include the findings of fact and conclusions of law that led them to their final decision. [[A.A.C. R12-5-2301 through 2315 Board of Appeals | Ariz. Admin. Code § R12-5-2314(B)]].  
  
 
==3-AZ-b.20 to 3-AZ-b.21 – Does the Developer Appeal the Decision?==
 
==3-AZ-b.20 to 3-AZ-b.21 – Does the Developer Appeal the Decision?==
The developer may appeal the decision of the Board through filing a request for rehearing or review of decision within 30 days following issuance of the final decision. [[A.A.C. R12-5-2301 through 2315 Board of Appeals | R12-5-2315(A)]]. The Board may grant a rehearing or review for any of the following reasons materially affecting the developer’s rights:
+
The developer may appeal the decision of the Board through filing a request for rehearing or review of decision within 30 days following issuance of the final decision. [[A.A.C. R12-5-2301 through 2315 Board of Appeals | Ariz. Admin. Code § R12-5-2315(A)]]. The Board may grant a rehearing or review for any of the following reasons materially affecting the developer’s rights:
 
*Irregularity in the proceedings or any order or abuse of discretion that deprived the developer of a fair hearing;
 
*Irregularity in the proceedings or any order or abuse of discretion that deprived the developer of a fair hearing;
 
*Misconduct of the Board, its staff, or the prevailing party;
 
*Misconduct of the Board, its staff, or the prevailing party;
Line 85: Line 89:
 
*Newly discovered material evidence that could not, with reasonable diligence, have been discovered and produced at the hearing;
 
*Newly discovered material evidence that could not, with reasonable diligence, have been discovered and produced at the hearing;
 
*Error in the admission or rejection of evidence or other errors of law occurring at the hearing or during the progress of the proceedings; or
 
*Error in the admission or rejection of evidence or other errors of law occurring at the hearing or during the progress of the proceedings; or
*The findings of fact or decision is not justified by the evidence or is contrary to law. [[A.A.C. R12-5-2301 through 2315 Board of Appeals | R12-5-2315(C)]].
+
*The findings of fact or decision is not justified by the evidence or is contrary to law. [[A.A.C. R12-5-2301 through 2315 Board of Appeals | Ariz. Admin. Code § R12-5-2315(C)]].
  
 
==3-AZ-b.22 – Participate in Rehearing or Review of Decision==
 
==3-AZ-b.22 – Participate in Rehearing or Review of Decision==
The Board may approve or deny the request for rehearing or review. [[A.A.C. R12-5-2301 through 2315 Board of Appeals | R12-5-2315(D)]]. The Board must conduct the rehearing or review within 90 days after issuing the order granting rehearing or review. [[A.A.C. R12-5-2301 through 2315 Board of Appeals | R12-5-2315(H)]].  
+
The Board may approve or deny the request for rehearing or review. [[A.A.C. R12-5-2301 through 2315 Board of Appeals | Ariz. Admin. Code § R12-5-2315(D)]]. The Board must conduct the rehearing or review within 90 days after issuing the order granting rehearing or review. [[A.A.C. R12-5-2301 through 2315 Board of Appeals | Ariz. Admin. Code § R12-5-2315(H)]].  
  
 
==3-AZ-b.23 to 3-AZ-b.24 – Does the Board Approve the Right-of-Way on Appeal?==
 
==3-AZ-b.23 to 3-AZ-b.24 – Does the Board Approve the Right-of-Way on Appeal?==
 
ASLD may approve or deny the right-of-way following rehearing or review.
 
ASLD may approve or deny the right-of-way following rehearing or review.
|Agency=Arizona State Land Department;
+
|Agency=[[Arizona State Land Department]];
 
|References=[[Arizona Right-of-Way Instruction Sheet | Right-of-Way Instruction Sheet]];
 
|References=[[Arizona Right-of-Way Instruction Sheet | Right-of-Way Instruction Sheet]];
 
[[Arizona State Land Department Rights-of-Way Website]];
 
[[Arizona State Land Department Rights-of-Way Website]];
 
[[Arizona State Land Department Applications and Permits Website]];
 
[[Arizona State Land Department Applications and Permits Website]];
 
[[Form RW-U: Utilities | Form RW-U]];
 
[[Form RW-U: Utilities | Form RW-U]];
|Regulations=[[A.R.S. § 37-102: State Land Department - Powers and Duties | A.R.S. 37-102]];
+
|Regulations=[[A.R.S. § 37-102: State Land Department - Powers and Duties | Arizona – Ariz .Rev. Stat. §§ 37-101–37-133, State Agencies and Officers]];
[[A.R.S. § 37-461: Grants of Rights-of-Way and Site for Public Uses | A.R.S. 37-461]];
+
[[A.R.S. § 37-461: Grants of Rights-of-Way and Site for Public Uses | Arizona – Ariz. Rev. Stat. §§ 37-201–37-620.31, Administration of State and Other Public Lands]];
[[A.A.C. R12-5-801: Rights-of-Way | A.A.C. R12-5-801]];[[A.A.C. R12-5-2301 through 2315 Board of Appeals | A.A.C. R12-5-2301 through 2315]]
+
[[A.A.C. R12-5-801: Rights-of-Way | Arizona – Ariz. Admin. Code §§ R12-5-801–R12-5-803, Rights-of-Way]];
 +
[[A.A.C. R12-5-2301 through 2315 Board of Appeals | Arizona –  Ariz. Admin. Code §§ R12-5-2301–R12-5-2315, Board of Appeals]]
 
}}
 
}}
 
{{RoadmapContact
 
{{RoadmapContact
 
|Contact=Vermont Agency of Commerce and Community Development: General Counsel
 
|Contact=Vermont Agency of Commerce and Community Development: General Counsel
 
}}
 
}}

Latest revision as of 14:39, 14 February 2020

RAPIDRegulatory and Permitting Information Desktop Toolkit
My Projects

Arizona State Land Right-of-Way (3-AZ-b)

Information current as of 2020
In Arizona, a developer may need a Right-of-Way from the Arizona State Land Department (ASLD) for transmission lines across lands owned by, belonging to and under the control of the state. Ariz. Rev. Stat. § 37-102. ASLD has the authority to grant ROWs, for any purpose it deems necessary, on and over state lands Ariz. Rev. Stat. § 37-461. ROWs may be subject to terms and conditions, as required by the ASLD. Transmission lines are generally permitted for a term of 50 years. Right-of-Way Instruction Sheet.


ASLD regulates rights-of-way pursuant to Ariz .Rev. Stat. §§ 37-101–37-133, Ariz. Rev. Stat. §§ 37-201–37-620.31, and Ariz. Admin. Code §§ R12-5-801–R12-5-803



State Land Right-of-Way Process


3-AZ-b.1 to 3-AZ-b.2 – Contact the Arizona State Land Department

Although the ROW process is technically initiated by the submission of an application, the developer may contact ASLD’s real estate division in order to discuss specific properties or to schedule a preliminary application conference. Because ROW applications are not posted online, they must be obtained directly from the ASLD. The Developer may pick up an application in person at the ASLD or contact the Rights-of-Way division and request that a copy be mailed. See Arizona State Land Department Rights-of-Way Website.

3-AZ-b.3 to 3-AZ-b.5 – Right-of-Way Application

As stated above, the ROW application process is technically initiated when the developer submits a ROW application to the ASLD. Entities that may apply for a ROW are listed in Ariz. Admin. Code § R12-5-801(C)(1)(a). A separate application must be submitted for each county crossed. See Ariz. Admin. Code § R12-5-801(C)(2). The following information must be included in the application:

  • Name and address of the developer;
  • Statement whether developer is an individual, partnership or corporation, or governmental agency of the state or political subdivision and municipal corporation thereof;
  • Statement of citizenship, when applicable;
  • If a corporation;
    • Name;
    • State of incorporation;
    • Arizona business address;
    • Affirmation of authority to do business in Arizona;
  • Age and marital status, when applicable;
  • Description, according to the public land survey of the land for which application is being made;
  • Width of the right-of-way;
  • The nature of the right-of-way (the right-of-way is temporary or permanent; the right-of-way requires exclusive use or to what extent; a right- of-way through a given area);
  • A survey of the land for which application is being made showing distance and direction from a known cadastral survey point in each section;
  • Location of improvements or crops on land under application over which proposed routes of right-of-way will pass (information required in Ariz. Admin. Code § R12-5-801(C)(3)(a)(ix) and Ariz. Admin. Code § R12-5-801(C)(3)(a)(x) must be conveyed by means of accurate plat or drawing accompanying the application form);
  • Evidence from surface lessee and all other right holders in the land applied for giving consent to the new right-of-way or objection thereto.

See Ariz. Admin. Code § R12-5-801(C)(3)(a). The application should also include information about what the developer proposes to construct and the purpose of the ROW. See the Right-of-Way Instruction Sheet. Supplemental forms may be required for specific types of ROW applications. For example, utilities must submit Form RW-U along with the ROW application. See Arizona State Land Department Applications and Permits Website. In addition, the ASLD may require the developer to submit additional information if necessary. See Ariz. Admin. Code § R12-5-801(C)(3)(b). The application must be accompanied by the appropriate filing fee, signed, and returned to the ASLD. Each application is reviewed by ASLD for completeness. See Ariz. Admin. Code § R12-5-801(C)(5)(a)-(b).

3-AZ-b.6 to 3-AZ-b.9 – Process Application

More complex ROW applications may take longer to process. Processing times vary from 12 to 16 months. See Arizona State Land Department Rights-of-Way Website. The ASLD conducts a preliminary review of the application to “evaluate impact and suitability as to the acceptability of the proposed alignment.” In some cases, a field inspection may be required. The developer will be notified if the alignment is acceptable. In some circumstances, additional surveys may be required. See the Right-of-Way Instruction Sheet. If the ASLD decides to approve the ROW, it will determine the rental fees after conducting an appraisal. See Ariz. Admin. Code § R12-5-801(C)(5)(c). The appraisal is based on the fair market value of the land. See the Right-of-Way Instruction Sheet.

3-AZ-b.10 – Does ASLD Approve the Right-of-Way?

ASLD may approve or deny the request for a right-of-way. If the right-of-way is not approved, then the developer may choose to appeal that decision to the Arizona Board of Appeals.

3-AZ-b.11 to 3-AZ-b.12 – Right-of-Way Contract

If the ASLD approves the ROW, it will draft a ROW contract that contains necessary terms and conditions. See Ariz. Rev. Stat. § 37-461. It must also provide for the following:

  • Payment to the [ASLD] of the amount established by the [ASLD] after determination of the true appraised value.
  • The installation and construction of necessary machinery, equipment and facilities with the right of removal within 90 days after expiration or termination of the right-of-way.
  • Fencing and other protective requirements deemed necessary by the [ASLD].
  • That the grantee (developer) must restore the surface of the land within the right-of-way to a reasonable condition as required by the [ASLD].
  • That the grantee (developer) will indemnify, hold and save grantor harmless against all loss, damage, liability, expenses, costs and charges incident to or resulting in any way from the use, condition or occupation of the land.
  • A statement of the purpose for which the right- of-way was granted.
  • The right of the grantee (developer) to assign the right-of- way, provided that such an assignment can not become effective until approved in writing by the [ASLD] as being in the best interests of the state and until a copy thereof is filed with the [ASLD].
  • The right of termination of the right-of-way by the grantee (developer) at any time during its term by giving the [ASLD] 30-days notice of termination in writing, provided that the grantee (developer) is not delinquent in any payments and has complied with all conditions on the date of termination.

See Ariz. Admin. Code § R12-5-801(D)(4).

The ASLD may also require the developer to post a bond to guarantee payment under the contract, guarantee restoration of the land after the ROW has expired, or cover loss associated with damage or destruction resulting from the construction or use of the ROW. See Ariz. Admin. Code § R12-5-801(D)(7). The ASLD issues the ROW contract once the developer has demonstrated compliance with all of the application requirements. The developer has 60 days from the date of mailing to execute and return the ROW contract with all applicable fees and rents. Failure to do so may result in the cancellation of the ROW. See Ariz. Admin. Code § R12-5-801(C)(8).

3-AZ-b.13 – Does the Developer Appeal the Decision?

The developer may appeal the decision not to approve the right-of-way to ASLD’s Commissioner.

3-AZ-b.14 – Notice of Appeal

The developer must file a written Notice of Appeal to ASLD containing a clear and concise statement of the grounds for appeal and the specific relief sought. Ariz. Admin. Code § R12-5-2302

3-AZ-b.15 – Set a Date for the Hearing

The County Clerk must set a date for the hearing within 10 days of receipt of the Notice of Appeal. Ariz. Admin. Code § R12-5-2303(A).

3-AZ-b.16 – Provide Notice of Hearing

The County Clerk must serve notice of the hearing, by certified mail or personal service, to the developer at least 30 days before the hearing. Ariz. Admin. Code § R12-5-2303(B). The Notice of Hearing must contain a statement:

  • Identifying the parties and matters asserted;
  • Establishing the date, time, and place of the hearing;
  • Identifying the legal authority and jurisdiction under which the hearing is to be held;
  • Advising the parties of the requirements of Ariz. Admin. Code § R12-5-2305;
  • Referencing the particular statutes and rules involved. Ariz. Admin. Code § R12-5-2303(B).

3-AZ-b.17 – Conduct Hearing on Decision

The Arizona State Land Department's Board of Appeals (Board) will conduct a hearing to review the decision to deny a right-of-way.

3-AZ-b.18 to 3-AZ-b.19 – Does the Board Approve the Right-of-Way?

The Board must render a final decision within 60 days after the hearing. Ariz. Admin. Code § R12-5-2314(A). The Board must include the findings of fact and conclusions of law that led them to their final decision. Ariz. Admin. Code § R12-5-2314(B).

3-AZ-b.20 to 3-AZ-b.21 – Does the Developer Appeal the Decision?

The developer may appeal the decision of the Board through filing a request for rehearing or review of decision within 30 days following issuance of the final decision. Ariz. Admin. Code § R12-5-2315(A). The Board may grant a rehearing or review for any of the following reasons materially affecting the developer’s rights:

  • Irregularity in the proceedings or any order or abuse of discretion that deprived the developer of a fair hearing;
  • Misconduct of the Board, its staff, or the prevailing party;
  • Accident or surprise that could not have been prevented by ordinary prudence;
  • Newly discovered material evidence that could not, with reasonable diligence, have been discovered and produced at the hearing;
  • Error in the admission or rejection of evidence or other errors of law occurring at the hearing or during the progress of the proceedings; or
  • The findings of fact or decision is not justified by the evidence or is contrary to law. Ariz. Admin. Code § R12-5-2315(C).

3-AZ-b.22 – Participate in Rehearing or Review of Decision

The Board may approve or deny the request for rehearing or review. Ariz. Admin. Code § R12-5-2315(D). The Board must conduct the rehearing or review within 90 days after issuing the order granting rehearing or review. Ariz. Admin. Code § R12-5-2315(H).

3-AZ-b.23 to 3-AZ-b.24 – Does the Board Approve the Right-of-Way on Appeal?

ASLD may approve or deny the right-of-way following rehearing or review.