Difference between revisions of "RAPID/BulkTransmission/New York/Transmission"

From Open Energy Information
(updating at a glance)
 
(2 intermediate revisions by 2 users not shown)
Line 4: Line 4:
 
|Topic=Transmission
 
|Topic=Transmission
 
|StateProcess=In New York, a bulk transmission developer may need to obtain a Certificate of Environmental Compatibility and Public Need from the [[New York State Public Service Commission]].
 
|StateProcess=In New York, a bulk transmission developer may need to obtain a Certificate of Environmental Compatibility and Public Need from the [[New York State Public Service Commission]].
 +
|SitingAuth=The [[New York State Public Service Commission]] has permitting authority over the siting and construction of electric transmission lines.
 +
|SitingProcess=New York does not have a comprehensive transmission siting process for transmission project development.
 +
|RegEntityDef=A person is defined as “any individual, corporation, public benefit corporation, political subdivision, governmental agency, municipality, partnership, co-operative association, trust or estate.” [[New York – Public Service Law|N.Y. Pub. Serv. Law §120 (2), Definitions]].
 +
|PubUtilTxCert=Any person may need a Certificate of Environmental Compatibility and Public Need from the [[New York State Public Service Commission]] to construct an electric transmission line of at least 125 kV that is at least one mile long or with a capacity between 100 kV and 125 kV that is at least 10 miles long. [[New York – Public Service Law|N.Y. Pub. Ser. Law §§ 120-130, Siting of Major Utility Transmission Facilities]].
 +
|SitingTimeframe=There is no statutorily defined timeframe for approval.
 
|GlanceTopic=Transmission
 
|GlanceTopic=Transmission
 
}}
 
}}

Latest revision as of 09:33, 15 June 2018

RAPIDRegulatory and Permitting Information Desktop Toolkit
My Projects

New York Bulk Transmission Siting & Regulation(8-NY)

In New York, a bulk transmission developer may need to obtain a Certificate of Environmental Compatibility and Public Need from the New York State Public Service Commission.

More Information

Determine Which State and Federal Permits Apply

Use this overview flowchart and following steps to learn which federal and state permits apply to your projects.


Permitting at a Glance

New York Federal

Transmission Siting: New York does not have a comprehensive transmission siting process for transmission project development.
Preemptive Authority: The New York State Public Service Commission has permitting authority over the siting and construction of electric transmission lines.
Regulated Entity Definition: A person is defined as “any individual, corporation, public benefit corporation, political subdivision, governmental agency, municipality, partnership, co-operative association, trust or estate.” N.Y. Pub. Serv. Law §120 (2), Definitions.
Public Utility Certificate Threshold: Any person may need a Certificate of Environmental Compatibility and Public Need from the New York State Public Service Commission to construct an electric transmission line of at least 125 kV that is at least one mile long or with a capacity between 100 kV and 125 kV that is at least 10 miles long. N.Y. Pub. Ser. Law §§ 120-130, Siting of Major Utility Transmission Facilities.
Processing Timeframe: There is no statutorily defined timeframe for approval.