Difference between revisions of "P.U.C. § 1002.3"

From Open Energy Information

m (Text replace - " Grid Connection" to "Transmission Siting & Interconnection")
(Removed from the Reference Library)
 
Line 36: Line 36:
 
|CourtName=
 
|CourtName=
 
|LegalYear=1951
 
|LegalYear=1951
|LegalCitation=P.U.C. § 1002.3  
+
|LegalCitation=P.U.C. § 1002.3
 
|WebPublicationPlace=
 
|WebPublicationPlace=
 
|WebPublisher=
 
|WebPublisher=
Line 55: Line 55:
 
|WebSiteURL=
 
|WebSiteURL=
 
|ReferenceURL=http://leginfo.legislature.ca.gov/faces/codes_displaySection.xhtml?lawCode=PUC&sectionNum=1002.3.
 
|ReferenceURL=http://leginfo.legislature.ca.gov/faces/codes_displaySection.xhtml?lawCode=PUC&sectionNum=1002.3.
|Abstract=This section includes some of the factors the Energy Commission shall consider as a basis for granting a certificate of public convenience and necessity.  
+
|Abstract=This section includes some of the factors the Energy Commission shall consider as a basis for granting a certificate of public convenience and necessity.
 
 
 
|ReferenceGenre=Bulk Transmission, Utilities
 
|ReferenceGenre=Bulk Transmission, Utilities
|RAPID=Yes
+
|RAPID=No
|RAPIDlocation=California
+
|RAPIDlocation=
|RAPIDtopic=Site Considerations,Transmission Siting & Interconnection
+
|RAPIDtopic=
 
|RAPIDsubtopic=
 
|RAPIDsubtopic=
 
}}
 
}}

Latest revision as of 08:38, 9 August 2016


OpenEI Reference LibraryAdd to library

Legal Document- Statute: P.U.C. § 1002.3

Abstract
This section includes some of the factors the Energy Commission shall consider as a basis for granting a certificate of public convenience and necessity.






Published 
N/A

Year Signed or Took Effect 
1951

Legal Citation 
P.U.C. § 1002.3


DOI 
Not Provided
Check for DOI availability: http://crossref.org


Online 
Internet link for P.U.C. § 1002.3
Citation

P.U.C. § 1002.3 (1951).